Pressurized turbine expansion machine, The working medium of this unit is pressurized by the booster first, and then enters into the main engine after coolingHeat exchanger, And then enter the expansion machine to generate adiabatic expansionAir separation equipmentThe cooling required by the unit, and the mechanical power generated at the same time is absorbed by the booster


The working medium enters the volute through the inlet pipe, then enters into the working wheel to work through the adjustable nozzle, and then is discharged through the expansion chamber and exhaust pipe. The air volume adjustment of the expansion machine is realized by the pneumatic film actuator installed on the top of the cold box to drive the blade of the nozzle to rotate, thus changing the sectional area of the channel, the stroke of the valve stem of the actuator reflects the change of the width of the nozzle channel. The total stroke of the valve stem is about 40mm. The downward movement of the valve stem makes the nozzle channel wide, while the upward movement is small.


Volute: it is welded with stainless steel structure, fixed on the fuselage, connected to the base through the fuselage, and the content of volute includes nozzle and expander impeller.

 
Rotor: the two ends are respectively equipped with the impeller of the expansion machine and the impeller of the booster (both of them are closed), which are a rigid rotor, fitted on the bearing of the body.


Bearings: both front and back bearings are radial thrust combined bearings, and clean and sufficient lubricating oil is supplied by the inlet pipe to make the rotor run stably for a long time. Platinum resistance thermometer is adopted to measure the bearing temperature.


Shaft seal: there is a maze seal sleeve on each shaft which is close to the second impeller to control the gas leakage within the minimum range, fill the sealing sleeve near the expansion machine with normal temperature Sealing Gas (dry air or nitrogen) to prevent the low temperature gas flowing through the expansion machine from leaking, and run "cold ", in order to control the pressure difference between the gas at the nozzle outlet and the sealing gas at the expansion machine end to maintain around 0.05MPa, a precise pressure reducing valve is specially set up, and the sealing sleeve at the booster end is filled in ~ Sealed Air with a pressure of 0.5MPa (dry air ).

DEAR Air Separation Solve YourWorking process and structure of booster turbine expanderYou can also learn about otherAir separation parts FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
The molecular sieve used in oxygen generators is the zeolite molecular sieve. It is a crystalline silica and aluminate polyhydric compound. Molecular sieves have a uniform pore size and their main function is to sieve molecules. There are three main types of molecular sieves: A, X and Y. The 13X molecular sieve is the only adsorbent currently used in liquid air separation plants. Any molecules that can be adsorbed on 3A, 4A and 5A molecular sieves can be adsorbed by 13X molecular sieves. It is c...
2026.09.30
Pressure test before valve installation 1. In the warranty period, those with the certification and the sealing surface is intact can no longer conduct the strength test alone, but only the air tightness test can be taken before installation. 2. Within the warranty period, it has the certificate, and its sealing surface has defects such as corrosion and damage. After treatment, it must carry out the air tightness test. 3. Outside the warranty period, those with certification and intact sealing surface shall be subject to air tightness test before installation. 4. For valves that need to be degreased and disassembled on site, air tightness test shall be conducted separately before installation. 5. The safety valve shall be sent to the local quality inspection department of the project for verification before the end of installation and commissioning.
2026.09.29
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top