Differential pressure gauges are set on the upper column, lower column, crude argon column and pure argon column of the air separation unit to measure the resistance of each column in the rectification process. The resistance value measured after the unit is started for the first time and adjusted to normal shall be used as the operation basis of the unit. When the resistance decreases, it indicates that there is liquid leakage, or the liquid level on the tray is too low, or the processing gas volume is insufficient (decreased). At this time, the reason must be found out. When the resistance increases, it is usually caused by the blockage of the tray. This situation can be eliminated only by heating the rectification column; If it is caused by load, the air intake and oxygen production shall be analyzed and adjusted according to the actual situation.

When the liquid level at the bottom of the rectification column rises too high, resulting in the submergence of the bottom tray, the column will be flooded. At this time, the resistance in the column will increase significantly, and it should be adjusted again after the liquid is discharged.

DEAR air separation has rich experience in project management, engineering design, procurement and infrastructure supporting services in the air separation industry, and is committed to providing customers with complete and efficient infrastructure supporting solutions to meet their needs. In the process of equipment manufacturing and installation, there are detailed management and operation requirements for each subdivisional equipment to ensure the high-quality operation of the equipment.

DEAR Air Separation Solve YourHow to operate and manage the rectification tower of air separation equipmentYou can also learn about otherLiquefied air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
1. Workers must wear safety helmets properly when entering the construction site, because the construction site is often chaotic. Some equipment installation sites, several construction teams are working at the same time, it is impossible to completely guarantee that there are no falling objects.2. Proper use of personal protective equipment, and carefully implement safety protection measures. When working on high places, cliffs and steep slopes without protective facilities, safety belts must b...
2024.05.16
The skid mounting of equipment refers to connecting the pipelines, equipment, pumps, control cabinets, electrical instruments and other components of the complete set into a whole according to the designed process flow, and fixing them on an integral base through welding, bolting and other connection methods. Without site installation, it can be directly completed the mechanical and electrical integration installation of the whole set in the plant area, then transporting and hoisting will be convenient.
2024.05.15
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top