当前位置: Home / Faq / Liquefied air separation FAQ /

Liquid air separation plant containers installation

Liquid air separation plant containers installation
Feb 15, 2022
Author: DEAR AST

 

  1. on the tower on the section of the sealing plate and pure nitrogen export cap, coarse argon tower condenser coarse argon export cap must be removed on the ground, clear clean aluminum chips with clean white cloth or plastic wrap before lifting in place.
  2. During the lifting of aluminium pressure vessels and aluminium pipelines, the installation should take protective measures to prevent damage to the surface, such as rigging jacket rubber tube, rigging between with support to open.
  3. The lower tower (has been compounded with the condenser) should be lifted with random lifting lugs. After the lower tower in place, with plumb line in the tower around check the verticality of the cold box, if the plumb line is not vertical, can be lined with thin steel plate under its base, verticality tolerance is not more than 05-1, verticality find accurate, pad iron should be with the lower raw surface car to avoid pad iron move.

3.1 main cold and on the connection of welding as far as possible with two people welding, preheating temperature and interlayer temperature control, welding shall be ventilated, the use of pumping, other containers with stainless steel composite pad plate of single-sided welding, preheating temperature and interlayer temperature is similarly controlled at about 1 ℃,.

3.2 argon arc welding nitrogen cylinder shall be placed nearby, preferably not more than 6 meters gas pipe the shorter the better, if the gas pipe is too long easy to bring in air, nitrogen, welding seam easy to produce bubbles and other phenomena, affecting the quality of welding both

3.3 In the case of air humidity greater than 8 (cloudy and rainy days, foggy weather) aluminum welding is not allowed.

3.4 butt grouping when the wrong side of the amount to be uniform, wrong side control in 5 wall thickness or less

3.5 aluminum tower butt, welding process must monitor the verticality of the tower, verticality can be adjusted according to the different orientation of the welding 

 

9

DEAR Air Separation Solve YourLiquid air separation plant containers installationYou can also learn about otherLiquefied air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
How many adsorbers are there in the purification system of air separation equipment?
2024.04.30
At the installation site of the air separation plant, we may see a variety of operation methods. We may be a little surprised when we first see it. We may get used to it if we see it many times. However, many accidents are caused by our negligence and carelessness. The following are some common sense of safe construction, hoping to be helpful to everyone: 1. Workers must wear safety helmets correctly when entering the construction site, because the construction site is often chaotic. Some equipment installation site, several construction teams are constructing at the same time, it is impossible to completely guarantee that there is no falling objects. 2. Use personal protective equipment correctly, and seriously implement safety protection measures. Safety belts must be fastened when constructing on high places, cliffs and steep slopes without protective facilities. 3. It is forbidden to climb the scaffold, safety protection facilities, etc. It is strictly prohibited to take the ele...
2024.04.29
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top