Pump installation precautions for cold box of large air separation unit

Pump installation precautions for cold box of large air separation unit
Feb 15, 2022
Author: DEAR AST

Check the level of the liner seat, level it and then tighten the foot nut and fill the base with cement slurry. After cement leveling, check whether the bolt holes are loose, tighten them after checking for suitability, and then check the level.

Coupling: The axis line of the pump and the axis line of the motor must coincide. This can be adjusted with thin shims. Measure the clearance of the two couplings, the difference between the maximum and minimum clearance on the plane of one week<0.3mm, the difference between the two ends of the centre line up and down or left and right<0.1mm. the final installation of the pump must also meet the manufacturer's installation requirements of large air separation unit.

The installation of protection brackets etc. needs to be carried out strictly as required.

The weakest point of the instrumentation pipe is the weld between the instrumentation pipe joint and the instrumentation pipe, the instrumentation pipe is used to import long distance instrumentation pipe, about 1000m/bundle, do not increase the number of socket welds in the cold box, the weld is installed outside the cold box as far as possible.

Dear Air provides quality services to customers to ensure the on-time delivery and operational safety of large air separation unit.

10

DEAR Air Separation Solve YourPump installation precautions for cold box of large air separation unitYou can also learn about otherLarge air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
The molecular sieve used in oxygen generators is the zeolite molecular sieve. It is a crystalline silica and aluminate polyhydric compound. Molecular sieves have a uniform pore size and their main function is to sieve molecules. There are three main types of molecular sieves: A, X and Y. The 13X molecular sieve is the only adsorbent currently used in liquid air separation plants. Any molecules that can be adsorbed on 3A, 4A and 5A molecular sieves can be adsorbed by 13X molecular sieves. It is c...
2026.09.30
Pressure test before valve installation 1. In the warranty period, those with the certification and the sealing surface is intact can no longer conduct the strength test alone, but only the air tightness test can be taken before installation. 2. Within the warranty period, it has the certificate, and its sealing surface has defects such as corrosion and damage. After treatment, it must carry out the air tightness test. 3. Outside the warranty period, those with certification and intact sealing surface shall be subject to air tightness test before installation. 4. For valves that need to be degreased and disassembled on site, air tightness test shall be conducted separately before installation. 5. The safety valve shall be sent to the local quality inspection department of the project for verification before the end of installation and commissioning.
2026.09.29
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top