Pre-installation inspection of the pipeline of small air separation unit

Pre-installation inspection of the pipeline of small air separation unit
Mar 26, 2026
Author: DEAR AST

Pipe of small air separation unit before installation, check the orientation of the container orifice, the orientation of the valve inlet and outlet is correct. The pipe fittings should be thoroughly cleaned ten net and strictly degreased, while opening the welding bevels etc. The welded pipe must be brushed with clean stainless steel wire for a very short time before welding.

In order to reduce the cold box pipe welding mouth, can be prefabricated in a clean plant, and later for the final distribution. Piping principles, first big pipe, then small pipe, first lower, then upper, first in charge, then auxiliary pipe.

The pipes must be naturally aligned before welding. Forced alignment with the help of manpower is never allowed, in order to avoid increased buttressing stress. If the pipework cannot be carried out continuously during installation, the openings must be covered or wrapped with plastic sheeting. The pipe rack in the cold box should be kept stable enough for the pipe rack to be installed and should not be shaken at will, taking into account the thermal expansion and contraction of the pipe and self-compensation, and in accordance with the requirements of the pipe rack diagram.

Dear Air's piping is checked in strict accordance with the standards before installation of small air separation unit to ensure the safety of the piping installation.4

DEAR Air Separation Solve YourPre-installation inspection of the pipeline of small air separation unitYou can also learn about otherSmall air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
Liquid air separation plant cold energy utilises air separation equipment, generally large air separation equipment with 2 combined expanders. The price is around 4 million RMB. The expansion air in the air separation plant is no longer required, so for the internal compression process air separation, the inlet air volume of the circulating booster is reduced by about 40% (from 5.A-2A). The energy consumption of the booster is reduced and the investment is reduced. Liquid air separation equipmen...
2026.06.18
1.In the process of preparation and implementation of hoisting construction, the safety and quality assurance system must ensure the normal operation,to ensure that the hoisting project meets the requirements of safety and quality. Before hoisting, safety and quality inspection must be carried out, and it must comply with the code forLifting construction of chemical engineering construction (HG20201-2000) and other regulations and specifications. 2.The crane performance shall meet the requirements of hoisting process, and the alarm and hydraulic system must be reliable. 3.Strictly implement the provisions of the technical documents attached to the crane. 4.The hoisting schedule of auxiliary crane should match that of main crane. 5.The hook deflection angle shall not be greater than 3°. 6.It is forbidden to drag the unitdirectly on the ground with crane. 7.Before unithoisting, trial hoisting shall be carried out. The clear hoisting distance and the foundation change at
2026.06.17
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top