Question Reply

After the air separation equipment stops, when the equipment does not discharge liquid, the basic temperature of the cold box will be reduced to more than - 100C in many cases. Most air separation plant users customers concern about this situation which will lead to a illusion of equipment leakage for the sake of safety.If the base temperature of cold box is reduced due to equipment leakage, the leakage should be more serious when the equipment hold pressure before the system stops. f the base temperature of the system is normal before shutdown, and the base temperature of the cold box decreases to more than minus 100 degrees after shutdown, it must be caused by no heating gas after shutdown of the air separation equipment and the downward diffusion of the cold gas in the fractionator, instead of the leakage of the fractionator.This phenomenon will disappear automatically after the equipment is put into normal operation.

DEAR Air Separation Solve YourAnalysis on the decrease of the base temperature of the cooling box after shutdown of the air separation plantYou can also learn about otherSmall air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
Liquid air separation plant cold energy utilises air separation equipment, generally large air separation equipment with 2 combined expanders. The price is around 4 million RMB. The expansion air in the air separation plant is no longer required, so for the internal compression process air separation, the inlet air volume of the circulating booster is reduced by about 40% (from 5.A-2A). The energy consumption of the booster is reduced and the investment is reduced. Liquid air separation equipmen...
2026.06.18
1.In the process of preparation and implementation of hoisting construction, the safety and quality assurance system must ensure the normal operation,to ensure that the hoisting project meets the requirements of safety and quality. Before hoisting, safety and quality inspection must be carried out, and it must comply with the code forLifting construction of chemical engineering construction (HG20201-2000) and other regulations and specifications. 2.The crane performance shall meet the requirements of hoisting process, and the alarm and hydraulic system must be reliable. 3.Strictly implement the provisions of the technical documents attached to the crane. 4.The hoisting schedule of auxiliary crane should match that of main crane. 5.The hook deflection angle shall not be greater than 3°. 6.It is forbidden to drag the unitdirectly on the ground with crane. 7.Before unithoisting, trial hoisting shall be carried out. The clear hoisting distance and the foundation change at
2026.06.17
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top