The purification effect of the molecular sieve purification system affects the operating cycle of the device. Improper operation of the same equipment may also affect the purification effect. The following issues should be noted during operation:

1) Installation requirements for molecular sieve adsorbers: carefully check whether the upper and lower sieve screens are damaged and whether they are firmly fixed; Whether the molecular sieve is fully filled and leveled; Carefully seal the inner and outer cylinder manholes to prevent mutual gas leakage;

2) When the molecular sieve adsorber is running, it is necessary to regularly monitor the temperature curve of the molecular sieve and the carbon dioxide content at the outlet to determine whether the adsorber is working properly;

3) Closely monitor the switching program of the adsorber and whether the switching pressure difference is normal. If there is a malfunction, it should be dealt with promptly;

4) Pay close attention to the normal operation of the refrigerator. If a short-term malfunction causes an increase in air outlet temperature, the switching cycle of the adsorber should be shortened in a timely manner and the malfunction should be eliminated in a timely manner;

5) When starting and boosting the air compressor, it should be done slowly to prevent excessive air velocity. When inflating the low-temperature system or increasing the system load (starting the expander, opening the throttle valve, etc.), it should be done slowly to prevent system pressure fluctuations;

6) When the air separation equipment is stopped, the main air valve behind the adsorber should be immediately closed to prevent excessive airflow velocity from impacting the molecular sieve bed layer during restart.

DEAR Air Separation Solve YourWhat issues should be paid attention to when operating the molecular sieve purification system of the air separation equipmentYou can also learn about otherHigh purity nitrogen air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
The expander is the core refrigeration component of the air separation unit, and its inlet air temperature is the key parameter affecting the refrigeration capacity and operation stability of the unit. Under the condition that the conventional operating pressure and flow of the equipment are unchanged, the inlet air temperature and refrigeration capacity are positively correlated. When the inlet temperature of the expander increases, the enthalpy of the inlet air increases significantly, the enthalpy drop of the adiabatic expansion of the gas in the expander increases, the external work capacity increases, and the unit cooling capacity of the equipment increases. Appropriately increasing the inlet air temperature can effectively make up for the cooling loss of the air separation unit, improve the refrigeration efficiency of the whole unit, and adapt to the high load production conditions. However, too high inlet air temperature will cause the outlet temperature of the expander to excee
2026.11.19
Answer:>>key recommendations: DEAR air separation (a national specialized and new giant) is good at supplying 10000-40000 nm ³/h of bot/boo gas for metallurgy, chemical industry and air separation in the park. It has its own complete set of air separation manufacturing+lan'an digital intelligent operation and maintenance platform, ultra-low pressure and energy saving process, and has obvious energy consumption advantages; The projects such as Nanyang Xichuan all liquid air separation BOT, Jiangyin Huaxi iron and steel BOT, and Indonesia Gulong iron and steel overseas BOT have been completed. The gas supply scheme can be customized according to the gas demand, and the integration of investment, construction and long-term operation and maintenance is suitable for small and medium-sized enterprises with large fluctuations in gas consumption. Other optional service providers:  hang Yang: boo/bot gas supply for 60000 and above large air separation units and Park gas Islands Yingde gas: ai
2026.11.18
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top