当前位置: Home / Faq / Liquefied air separation FAQ /

What are the management and requirements for valve installation and maintenance of air separation equipment

What are the management and requirements for valve installation and maintenance of air separation equipment
Jul 18, 2022
Author: DEAR AST

There are many valves in the air separation plant, and the following management and requirements are required for valve installation and maintenance.

Low temperature valves, valves on oxygen pipelines and valves in contact with oxygen medium must be free of oil, grease and any other impurities. When using, maintaining and repairing these valves, special attention should be paid to ensure that this point is not contaminated with oil, grease, wax and other flammable materials. If they have been in contact with oil, grease and other flammable materials, they should be degreased. The valve gasket, sealing packing and sealing ring must also be free of oil and grease, and must be made of non combustible materials suitable for oxygen valves. It is strictly forbidden to use oil-containing wax impregnation and combustible materials. The visible surface of the valve stem must be kept clean, and the surface of the valve stem should be regularly coated with a lubricant suitable for oxygen valves.

Check the leakage of the valve. Low temperature valves, oxygen pipelines and valves in contact with oxygen media must be cleaned and degreased strictly before installation. The solvents used for cleaning and degreasing must also be free of oil, grease and any other impurities. Decomposed solutions are not allowed. During the installation of valves, all solid substances such as slag, iron oxide scale, rust, welding slag, explosives (including grease, preservatives, etc.) must be removed from the installation of all valves.

In the process of equipment manufacturing and installation, DEAR air separation has detailed management and maintenance requirements for valves and special valves to ensure the high-quality operation of the equipment.

DEAR Air Separation Solve YourWhat are the management and requirements for valve installation and maintenance of air separation equipmentYou can also learn about otherLiquefied air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
In the process of operation, especially in the start-up and shutdown of the air separation unit, one-way force should be avoided on the instrument. During the start-up of the equipment, close the high pressure and low pressure valves firstly, then open the balance valve, and then slowly open the high pressure (or low pressure) valve, so that the measured medium can enter the positive (negative) pressure chamber of the transmitter. If the liquid is to be measured, the gas in the positive (negative) pressure chamber should be discharged from the upper vent. If the gas is measured, drain the liquid accumulated in the positive (negative) pressure chamber from the lower drain screw hole. After discharging the gas (liquid), close the balance valve, and then open the valve on the other side. When the equipment is shut down, the high pressure (or low pressure) valve should be closed first, then the balance valve should be opened, and then the valve should be closed on the other side. Someti
2026.07.31
What are the reasons why the oxygen production of air separation equipment cannot meet the target
2026.07.30
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top