What measures should be taken in case of failure of booster turbine expander of air separation unit

What measures should be taken in case of failure of booster turbine expander of air separation unit
Jul 12, 2022
Author: DEAR AST

When the alarm device of the booster turbine expander of the air separation unit rings, it is the signal of the failure of the booster turbine expander. Consequences: the pressure of the processing air increases, affecting the operation of the air turbine compressor, and the liquid level of the main condensing evaporator decreases, resulting in a decrease in output.

Emergency measures shall be taken in case of failure of booster turbine expander of air separation unit:

Start the standby booster turbine expander; Adjust the discharge pressure of the booster compressor to stabilize the discharge pressure of the booster compressor, check the purity of the product gas, reduce the product volume, reduce the liquid discharge volume, or stop completely if necessary.

Further measures: eliminate the fault immediately; Adjust the air volume and output to normal values.

The common failure of booster turbine expander is the blockage caused by ice and dry ice, which requires heating. As for other faults, the causes should be found out and eliminated according to the regulations on the use and maintenance of booster turbine expander.

DEAR air separation equipment manufacturing technology has studied technical theories and principles through long-term experience, and the manufacturing technology is mature and standardized. Each sub equipment has formulated use and maintenance regulations, and strictly controlled each stage, with quality first, to ensure the safety and efficiency of the equipment.

DEAR Air Separation Solve YourWhat measures should be taken in case of failure of booster turbine expander of air separation unitYou can also learn about otherAir separation parts FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
1. Workers must wear safety helmets properly when entering the construction site, because the construction site is often chaotic. Some equipment installation sites, several construction teams are working at the same time, it is impossible to completely guarantee that there are no falling objects.2. Proper use of personal protective equipment, and carefully implement safety protection measures. When working on high places, cliffs and steep slopes without protective facilities, safety belts must b...
2024.05.16
The skid mounting of equipment refers to connecting the pipelines, equipment, pumps, control cabinets, electrical instruments and other components of the complete set into a whole according to the designed process flow, and fixing them on an integral base through welding, bolting and other connection methods. Without site installation, it can be directly completed the mechanical and electrical integration installation of the whole set in the plant area, then transporting and hoisting will be convenient.
2024.05.15
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top