How to blast and purge the pressure pipe

How to blast and purge the pressure pipe
Jul 17, 2023
Author: DEAR AST

Steel pipes shall be flushed and purged as required after passing the strength test and before the pneumatic tightness test.

For many years, water flushing, air purging, steam purging and other technologies have been mainly used for flushing and purging. This is more effective for small-diameter pipelines. For pipelines with larger diameters, the ideal purging effect is often not achieved because the flow rate of purging medium cannot meet the specified requirements. As the pipeline accessories and instruments become more and more advanced, and the requirements of production technology continue to improve, some construction technologies can no longer meet the construction requirements. In the purging and flushing construction of large-diameter steel pipelines, the blasting purging method is replacing other construction methods used in the past.

Blasting purging is to close one end of the purged pipe with a bursting disc whose strength is much lower than that of the pipe, and inject compressed air into the other end. The air pressure in the system gradually increases. When the pressure exceeds the limit pressure that the bursting disc can bear, the bursting disc will suddenly rupture, and the compressed air in the system will instantly expand rapidly and eject from the bursting opening at a very high speed. At the same time, the welding slag and other sundries in the pipeline will also be discharged under the vibration caused by blasting and the impact of high-speed air flow. Repeated several times, the purging requirements can be achieved.  

The production of air separation equipment and oxygen pipelines of Deere air separation plant strictly comply with the requirements of process technical specifications, and the production and installation of pipelines ensure the high quality requirements of the overall air separation plant.

DEAR Air Separation Solve YourHow to blast and purge the pressure pipeYou can also learn about otherBiogas purification FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
The plant operation cycle between two large heating is related to many factors. From an operational point of view, this mainly depends on when the air passage of the main heat exchanger is blocked. The main reason for the blockage is that the moisture and carbon dioxide content in the air entering the unit exceeds the standard, which accumulates and freezes in the main heat exchanger until it is blocked. The abnormal operation of molecular sieve purification system will shorten the operation cycle of the unit. It is mainly caused by the following reasons: 1. The molecular sieve adsorption bed is short circuited. In the process of operation, due to the unstable gas velocity control or switching, the pressure difference between the two tanks is too large, which will affect the bed layer, make the molecular sieve bed uneven and make the bed layer short circuit. In serious cases, the dust screen of the adsorber will break and the molecular sieve powder will enter the heat exchanger c
2026.03.30
What is the oxygen internal compression process
2026.03.27
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top