Overhaul of condenser of small air separation units

Overhaul of condenser of small air separation units
May 20, 2022
Author: DEAR AST

1 main exchange cold box and the main cold box between the partition, process pipeline through the partition using the insulation plate plus wool felt cold way, its poor cooling effect, resulting in the partition, column channel steel frost cracking. So the workers changed to open DN600 hole on the partition plate plus stainless steel collar, the collar with foam foam to keep cold, welding reinforcement of frozen cracked channel steel branch.
2 original process pipeline fixed using stainless steel clamps wool felt appears more loose, check all process pipelines, according to the new specifications to increase the bracket as follows
3The blow-off pipe line of the liquid argon return pipe of the crude argon condenser (Φ30×2), increase the fixed frame and guide frame
4 The liquid-air return line of the crude argon condenser to the upper tower (LAΦ30×2-L), add fixed frame and guide frame near the exit end of the crude argon condenser. Replace the pipe before and after the manual valve V701, make brackets for each of the main tower crude argon II tower, and add fixed brackets before the inlet of the upper tower.
5 crude argon condenser process argon to fine argon tower pipeline (GA-Φ70×3--), the original pipe rack removed, in the original position to increase the fixed in the crude argon tower II fixed pipe rack, process argon discharge pipe in the middle of the fine argon tower to increase a guide rack.
6 liquid air into the crude argon condenser pipeline (LA-①110×4-L) the upper part of the original pipe rack was removed and replaced with a fixed pipe rack on the crude argon tower from the top to the first pipe rack near the cold box was changed to a frame type sliding rack.
The small air separation unit, large air separation unit and liquid air separation plant overhaul team at DEAR Air is experienced in overhauling condensers.缅甸钢铁公司-1500

DEAR Air Separation Solve YourOverhaul of condenser of small air separation unitsYou can also learn about otherSmall air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
How many adsorbers are there in the purification system of air separation equipment?
2024.04.30
At the installation site of the air separation plant, we may see a variety of operation methods. We may be a little surprised when we first see it. We may get used to it if we see it many times. However, many accidents are caused by our negligence and carelessness. The following are some common sense of safe construction, hoping to be helpful to everyone: 1. Workers must wear safety helmets correctly when entering the construction site, because the construction site is often chaotic. Some equipment installation site, several construction teams are constructing at the same time, it is impossible to completely guarantee that there is no falling objects. 2. Use personal protective equipment correctly, and seriously implement safety protection measures. Safety belts must be fastened when constructing on high places, cliffs and steep slopes without protective facilities. 3. It is forbidden to climb the scaffold, safety protection facilities, etc. It is strictly prohibited to take the ele...
2024.04.29
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top