The acetylene content in liquid air and liquid oxygen needs to be analysed every day, so the liquid air and liquid oxygen discharge valves have to be operated every day.

The problem arises when it is easy to open the valve, but difficult to close it, sometimes even a little can not be closed. This is mainly due to the presence of moisture at the valve stuffing box. When the liquid is discharged, the temperature drops and freezing occurs. In order to prevent this, the valve should be turned continuously at the beginning of the discharge of the liquid so that the stem does not freeze. If freezing has occurred, steam can be used to heat the stuffing box before it is closed.

Dear Air Separation has a lot of practical experience in all aspects of technology, piping and valves in the long-term small air separation units manufacturing and design process, requiring high quality large air separation units and liquid air separation plants and providing a full range of technical services to customers.

上海宝冶集团有限公司-7500(2)

DEAR Air Separation Solve YourWhy does the large air separation units liquid drain valve not close?You can also learn about otherLarge air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
The molecular sieve used in oxygen generators is the zeolite molecular sieve. It is a crystalline silica and aluminate polyhydric compound. Molecular sieves have a uniform pore size and their main function is to sieve molecules. There are three main types of molecular sieves: A, X and Y. The 13X molecular sieve is the only adsorbent currently used in liquid air separation plants. Any molecules that can be adsorbed on 3A, 4A and 5A molecular sieves can be adsorbed by 13X molecular sieves. It is c...
2026.09.30
Pressure test before valve installation 1. In the warranty period, those with the certification and the sealing surface is intact can no longer conduct the strength test alone, but only the air tightness test can be taken before installation. 2. Within the warranty period, it has the certificate, and its sealing surface has defects such as corrosion and damage. After treatment, it must carry out the air tightness test. 3. Outside the warranty period, those with certification and intact sealing surface shall be subject to air tightness test before installation. 4. For valves that need to be degreased and disassembled on site, air tightness test shall be conducted separately before installation. 5. The safety valve shall be sent to the local quality inspection department of the project for verification before the end of installation and commissioning.
2026.09.29
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top