Precautions for installation of precooling system

Precautions for installation of precooling system
Jan 15, 2021
Author: DEAR AST
Question Reply

1.Before the air cooling columnand water cooling columnare hoisted in place, the anchor hole shall be cleaned, and there shall be no water and debris in the anchor hole.

 

2.After the air cooling columnand water cooling columnare hoisted in place, the perpendicularity of the equipment shall be checked. The perpendicularity shall be ≤ 1/1000 and the total length shall not exceed 10mm.

 

3.The bottom of the anchor bolt shall not touch the bottom of the reserved anchor hole. After tightening the nut, the bolt shall be exposed for about 2 nut distances.

 

4.The piping of air, nitrogen and crudenitrogen into air cooling columnand water cooling column shall be sealed to prevent backflow.

 

5.After the cooling water pump and freezing water pump are installed in place, check the concentricity of the water pump and the motor to ensure that the axis line of the water pump and the axis line of the motor must coincide.

 

6.The installation position of the water filter shall be convenient for the removal of the filter element and the maintenance and replacement of the filter element. After the single unit test run, the water filter should be removed and washed once, and then put into normal use.

 

7.The refrigeration unit shall be installed according to the installation requirements of the manufacturer.

DEAR Air Separation Solve YourPrecautions for installation of precooling systemYou can also learn about otherLarge air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
The plant operation cycle between two large heating is related to many factors. From an operational point of view, this mainly depends on when the air passage of the main heat exchanger is blocked. The main reason for the blockage is that the moisture and carbon dioxide content in the air entering the unit exceeds the standard, which accumulates and freezes in the main heat exchanger until it is blocked. The abnormal operation of molecular sieve purification system will shorten the operation cycle of the unit. It is mainly caused by the following reasons: 1. The molecular sieve adsorption bed is short circuited. In the process of operation, due to the unstable gas velocity control or switching, the pressure difference between the two tanks is too large, which will affect the bed layer, make the molecular sieve bed uneven and make the bed layer short circuit. In serious cases, the dust screen of the adsorber will break and the molecular sieve powder will enter the heat exchanger c
2026.03.30
What is the oxygen internal compression process
2026.03.27
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top