Pressure test before valve installation

 

1.In the warranty period, those withthe certificationand the sealing surface is intact can no longer conduct the strength test alone, but only the air tightness test can be taken before installation.

 

2.Within the warranty period, it has the certificate, and its sealing surface has defects such as corrosion and damage. After treatment, it must carry out the air tightness test.

 

3.Outside the warranty period, those with certificationand intact sealing surface shall be subject to air tightness test before installation.

 

4.For valves that need to be degreased and disassembled on site, air tightness test shall be conducted separately before installation.

 

5.The safety valve shall be sent to the local quality inspection department of the project for verification before the end of installation and commissioning.

DEAR Air Separation Solve YourPressure test and sealing test of valves in cold box of air separation unitYou can also learn about otherLarge air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
The non-power consuming option for liquid air separation plants can be used for full liquid air separation plants,where the produced liquid is sold off. This approach is currently available for most LNG receiving stations. For air separation units with a large cold capacity, the liquid air can be pressurised to 6baA in a vacuum storage tank, and then heat exchanged through a heat exchanger, instead of the air compressor, directly into the cold box for distillation. At the same time in the cold b...
2026.03.13
1. Before connecting the pipe orifice of each container, clean white cloth shall be used to tie the orifice to prevent grease and dirt from entering. 2. When welding in the cold box and in the condensing evaporator, it is strictly forbidden for flame or arc to touch the surface of vessels and pipes. 3. The containers, valves, pipes and corresponding supports in the cold box, the surface of the cold box and the foundation surface shall not be stained with grease after installation, otherwise, degreasing treatment shall be carried out.
2026.03.12
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top