Full low pressure oxygen generatorIn case of emergency power failure, the first task is to open the air release valve at the end of the air compressor and close the valve that air enters the distillation column quickly, in case that the air compressor reverses compressed air and burns the bearing because of the failure of the outlet check valve of the air compressor. Follow these steps:
1) turn the switching mechanism from automatic to manual, and close the forced Valve and average pressure switching valve of air entering the tower. Open the sewage nitrogen vent valve.
2) cut off the solenoid valve of the expansion machine, and close the inlet regulating valve of the expansion machine and the inlet and outlet valves of the expansion machine.
3) close the regulating valve of liquid, liquid nitrogen and sewage nitrogen.
4) turn off all the oxygen and nitrogen products and send them out of the valve, and open the vent valve, then put the three-way valve of dirt and nitrogen in the vent side.
5) turn off all the inflated air to enter the disc valve of the upper tower, and open the bypass valve.
6) close the oxygen regulating disc valve, and fully open the dirt nitrogen and pure nitrogen regulating disc valve.
7) turn off the steam gas source of the steam heater.
8) cut off the power switch of the electrical equipment and make it in the starting position.
After finding out the cause of the power failure and eliminating the failure, be ready to start the car.

DEAR Air Separation Solve YourHow to operate the all-low-voltage capturing machine when it encounters emergency power failure?You can also learn about otherSmall air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
How many adsorbers are there in the purification system of air separation equipment?
2024.04.30
At the installation site of the air separation plant, we may see a variety of operation methods. We may be a little surprised when we first see it. We may get used to it if we see it many times. However, many accidents are caused by our negligence and carelessness. The following are some common sense of safe construction, hoping to be helpful to everyone: 1. Workers must wear safety helmets correctly when entering the construction site, because the construction site is often chaotic. Some equipment installation site, several construction teams are constructing at the same time, it is impossible to completely guarantee that there is no falling objects. 2. Use personal protective equipment correctly, and seriously implement safety protection measures. Safety belts must be fastened when constructing on high places, cliffs and steep slopes without protective facilities. 3. It is forbidden to climb the scaffold, safety protection facilities, etc. It is strictly prohibited to take the ele...
2024.04.29
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top