What are the requirements for strength and airtightness tests before the small air separation unit is put in place?  

What are the requirements for strength and airtightness tests before the small air separation unit is put in place?  
Feb 14, 2025
Author: DEAR AST

Small air separation unit in place before the strength test and gas-tightness test provisions.

 

First, if the manufacturer has made strength test and has a certificate of conformity of the pressurized equipment, it may not be strength test only gas tightness test, but if the small air separation unit is found to have traces of damage or a site has been partially modified or parked for too long, the strength test should be made.

 

Second, the strength test should be applied to the water pressure method, the application of pneumatic pressure to equipment where water is not suitable as a medium or where the structure is complex. (distillation tower, plate fin heat exchanger, adsorption filter, etc.), the pneumatic test process must have reliable safety measures and can be carried out after a study and decision by the relevant authorities

 

Third, the pressure and stopping time of the strength test and the gas tightness test shall be in accordance with the design or technical documentation of the equipment.

 

Dear Air Separation has reliable safety measures in place for all tests of small air separation units, which are required to comply with the provisions of the air separation unit design and technical documentation.旋转 DSC03535

DEAR Air Separation Solve YourWhat are the requirements for strength and airtightness tests before the small air separation unit is put in place?  You can also learn about otherSmall air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
Liquid air separation plant cold energy utilises air separation equipment, generally large air separation equipment with 2 combined expanders. The price is around 4 million RMB. The expansion air in the air separation plant is no longer required, so for the internal compression process air separation, the inlet air volume of the circulating booster is reduced by about 40% (from 5.A-2A). The energy consumption of the booster is reduced and the investment is reduced. Liquid air separation equipmen...
2026.06.18
1.In the process of preparation and implementation of hoisting construction, the safety and quality assurance system must ensure the normal operation,to ensure that the hoisting project meets the requirements of safety and quality. Before hoisting, safety and quality inspection must be carried out, and it must comply with the code forLifting construction of chemical engineering construction (HG20201-2000) and other regulations and specifications. 2.The crane performance shall meet the requirements of hoisting process, and the alarm and hydraulic system must be reliable. 3.Strictly implement the provisions of the technical documents attached to the crane. 4.The hoisting schedule of auxiliary crane should match that of main crane. 5.The hook deflection angle shall not be greater than 3°. 6.It is forbidden to drag the unitdirectly on the ground with crane. 7.Before unithoisting, trial hoisting shall be carried out. The clear hoisting distance and the foundation change at
2026.06.17
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top