First, check the appearance of the pipeline to confirm that all pipelines are:

1) Arrange the construction according to the design, and mark the type of gas.

2) All materials used conform to the requirements.

3) The welding of the pipeline is in accordance with the specification, and the angle is free from misalignment, inclination and distortion.

4) There is no dirt left in the pipeline.

5) The pipeline has no defects such as depression and crack.

Then the pressure holding test is carried out

1) Open the end valves of all gas lines.

2) Close the end valve of the gas pipeline to be tested.

3) Fill the gas pipeline to be tested with N2 to a certain pressure and observe for five minutes to see if the pressure gauge drops.

4) If the pressure gauge does not drop, it means that the pipeline connection is correct. If there is no drop phenomenon, open the end valve of the gas pipeline to be tested to judge whether the pressure gauge will drop to zero. If it drops to zero, it means that the pressure gauge has no problem. Then pipeline pressure test and air tightness test are carried out

1) Use 0.1 μ Pressure test the nitrogen or pN2 system filtered by M filter.

2) The design value of pressure and pressurization time should be in accordance with the design requirements.

3) After the pipeline is filled with the gas of the specified pressure, check all the connected and welded parts, and use the leak detection fluid to detect the leakage, maintain a certain pressure in the pipeline and make records.

4) Record any outliers found.

5) Record the data read by the pressure gauge in use.

6) After the completion of the pressure test, start the air tightness test.

DEAR is actively promoting "industry 4.0", based on the deep integration of new generation information and communication technology and advanced manufacturing technology, relying on automatic production technology to build enterprise intelligent upgrading, and help customers achieve rapid growth.

Intelligent Manufacturing: energy saving and efficiency, benefit customers. Clearly grasp the production and marketing process; Improve the controllability of production; Reduce manual intervention.

Remote equipment monitoring: efficient operation, create profits together. It can be monitored and forewarned; Accurately grasp the fault information; Remote diagnosis and rapid solution.

Provincial air separation engineering technology research center: combination of production and research to promote transformation. Give full play to the advantages of resources; Improve the efficiency of project research; We will promote the upgrading of the industrial revolution.

DEAR air separation design and Research Institute: make great efforts to make breakthroughs. Employ high-end talents; Won a number of patents; Help customers grow.

DEAR air separation has been focusing on the manufacturing and service of large-scale air separation equipment and cryogenic air separation for nearly 20 years. It has rich experience in project engineering, and constantly uses innovative technologies to optimize equipment energy saving and safety. DEAR air separation strives to bring higher benefits to customers.

DEAR Air Separation Solve YourTest process of stainless steel pipe in air separation unitYou can also learn about otherLiquefied air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
Liquid air separation plant cold energy utilises air separation equipment, generally large air separation equipment with 2 combined expanders. The price is around 4 million RMB. The expansion air in the air separation plant is no longer required, so for the internal compression process air separation, the inlet air volume of the circulating booster is reduced by about 40% (from 5.A-2A). The energy consumption of the booster is reduced and the investment is reduced. Liquid air separation equipmen...
2026.06.18
1.In the process of preparation and implementation of hoisting construction, the safety and quality assurance system must ensure the normal operation,to ensure that the hoisting project meets the requirements of safety and quality. Before hoisting, safety and quality inspection must be carried out, and it must comply with the code forLifting construction of chemical engineering construction (HG20201-2000) and other regulations and specifications. 2.The crane performance shall meet the requirements of hoisting process, and the alarm and hydraulic system must be reliable. 3.Strictly implement the provisions of the technical documents attached to the crane. 4.The hoisting schedule of auxiliary crane should match that of main crane. 5.The hook deflection angle shall not be greater than 3°. 6.It is forbidden to drag the unitdirectly on the ground with crane. 7.Before unithoisting, trial hoisting shall be carried out. The clear hoisting distance and the foundation change at
2026.06.17
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top