当前位置: Home / Faq / Large air separation FAQ /

Main causes and preventive measures of welding cracks in aluminum alloy TIG welding

Main causes and preventive measures of welding cracks in aluminum alloy TIG welding
Feb 18, 2025
Author: DEAR AST
Question Reply

The main causes are as follows:

1.The structure is unreasonable, the welding seam is concentrated and the welding joint stress is too large.

2.When welding, the molten pool is too large and overheated, and the alloy is burnt too much.

3.The arc crater is not filled due to too fast arc closing and too early wire drawing.

4.Material problems, for example, when Mg content is less than 3%, and impurities such as Fe and s exceed the standard, it is easy to cause cracks.

When the melting temperature of welding wire is too high, liquefaction cracks in heat affected zone are easy to occur.

 

Preventive measures include:

1.During the design, attention should be paid to the reasonable arrangement of welding seams, avoiding the stress concentration as far as possible, and selecting the welding sequence reasonably.

2.Reduce welding current or increase welding speed properly.

3.The arc stopping operation technology should be correct, and the arc pit should be filled by adding the outlet plate or using the current attenuation device.

4.Choose welding materials correctly.

DEAR Air Separation Solve YourMain causes and preventive measures of welding cracks in aluminum alloy TIG weldingYou can also learn about otherLarge air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
The main heat exchanger is the key equipment to ensure the performance of the air separation plant. Its functions in the air separation plant of the molecular sieve pre-filtration process are as follows: recover the cooling capacity of the reflux gas, ensure that the heat exchange temperature difference is within the design range; provide sufficient expansion gas in front of the expander to make up for the cooling loss of the air separation plant; provide raw air for the lower tower under the design conditions; and the working medium is in the main heat exchanger The resistance value in meets the process requirements.
2025.12.31
A low pressure nitrogen expander is added to the process design. The pressure nitrogen from the pressure tower and high pressure expander is expanded into low pressure nitrogen, which is combined with the nitrogen coming from the low pressure tower and fed into the charge gas compressor. This is specially set up for rapid oxygen load changes. The oxygen product flow rate during normal operation corresponds to the amount of oxygen contained in the amount of air entering the air separation unit. T...
2025.12.30
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?