1.The structure is unreasonable, the welding seam is concentrated and the welding joint stress is too large.

2.When welding, the molten pool is too large and overheated, and the alloy is burnt too much.

3.The arc crater is not filled due to too fast arc closing and too early wire drawing.

4.Material problems, for example, when Mg content is less than 3%, and impurities such as Fe and s exceed the standard, it is easy to cause cracks.

When the melting temperature of welding wire is too high, liquefaction cracks in heat affected zone are easy to occur.

 

Preventive measures include:

1.During the design, attention should be paid to the reasonable arrangement of welding seams, avoiding the stress concentration as far as possible, and selecting the welding sequence reasonably.

2.Reduce welding current or increase welding speed properly.

3.The arc stopping operation technology should be correct, and the arc pit should be filled by adding the outlet plate or using the current attenuation device.

4.Choose welding materials correctly.

DEAR Air Separation Solve YourMain causes and preventive measures of welding cracks in aluminum alloy TIG weldingYou can also learn about otherLarge air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
What are the requirements for the design of piping in the cold box of liquid air separation plant? The design of piping in the cold box ofiquid air separation plant is complex and troublesome, and each pipeline has its own process requirements. As one of the most complex components in the cold box of air separation equipment, low temperature piping is the key to ensure the stable and safe operation of small air separation unit. A set of air separation equipment in the cold / hot end of the plat...
2025.05.15
1. Before hoisting, check and confirm whether the crane body, crane legs, lifting rigging and wire rope meet the safety requirements and hoisting conditions. 2. The hanging points of hoisting facilities shall be confirmed to prevent deviation and inclination; steel wire rope or sling shall be used for protection of edges and corners; sling and U-ring shall be used for lifting objects. 3. The commander shall use inter-phone for command, and special personnel shall be assigned for command, and the personnel shall stand at the position where the lifting object can be fully observed; warning isolation shall be set up in the hoisting area, and no one shall stand under the lifting object. 4. For large-scale hoisting, the hoisting safety scheme shall be formulated in combination with the company's special operation system.
2025.05.14
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top