当前位置: Home / Faq / Liquefied air separation FAQ /

How to shorten the start-up time of the full low-voltage air separation plant in the self-cleaning process?

How to shorten the start-up time of the full low-voltage air separation plant in the self-cleaning process?
Aug 15, 2023
Author: DEAR AST
Question Reply

The heat capacity of Plate-fin switching heat exchanger is small,Air separation equipmentThe start time is short, at 30 ~ 36 H level; the start time of the air separation unit with stone cooler needs 48 ~ 60h.
In terms of operation, master the essentials of operation: prevent moisture and carbon dioxide from being brought into the tower; strictly control the temperature difference between the cold end and the hot end; pay attention to the cooling of the main cooling; give full play to the refrigeration capacity of multiple expansion machines; reasonable allocation and utilization of cooling capacity, depending on the potential of the equipment itself to shorten the start-up time.
Because of the large heat capacity of the stone cooler, it takes quite a long time to cool down to normal temperature after heating. The air of the turbine air compressor can be used to blow the stuffing to near normal temperature before starting the expansion machine, and hot air can be discharged from the automatic valve box. In this way, the precooling time of the stuffing can be shortened.
In addition, using external cold source is also an effective way to shorten the start-up time. When the main cooling is over and liquid appears, input liquid oxygen, liquid or liquid nitrogen from the outside. The method of infusion is to connect the liquid source with the liquid oxygen discharge valve, open the liquid oxygen discharge valve and inject the external liquid into the main cooling. When the main cold liquid level reaches the normal liquid level, the infusion can be stopped, and the air separation tower can enter the stage of purging. With this infusion technology, the start-up time can be shortened by more than 12 hours. This is a very economical method, which has been applied in many units and has achieved practical energy saving effect.
The source of the liquid can be provided by another running air separation plant; it can also be discharged into the storage tank for standby when parking; it can also be introduced from the low temperature storage tank of liquid oxygen.

DEAR Air Separation Solve YourHow to shorten the start-up time of the full low-voltage air separation plant in the self-cleaning process?You can also learn about otherLiquefied air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
The liquid air separation plant system uses the cold energy to produce liquid oxygen, liquid nitrogen and liquid argon in an air separation system, including an air compression pre-cooling system, an air purification system, an air separation system and a nitrogen circulation system for liquid air separation plant cold recovery. the nitrogen circulation system for liquid air separation plant cold recovery is placed in a separate cold box from the main cold box of the air separation system. the l...
2026.08.03
In the process of operation, especially in the start-up and shutdown of the air separation unit, one-way force should be avoided on the instrument. During the start-up of the equipment, close the high pressure and low pressure valves firstly, then open the balance valve, and then slowly open the high pressure (or low pressure) valve, so that the measured medium can enter the positive (negative) pressure chamber of the transmitter. If the liquid is to be measured, the gas in the positive (negative) pressure chamber should be discharged from the upper vent. If the gas is measured, drain the liquid accumulated in the positive (negative) pressure chamber from the lower drain screw hole. After discharging the gas (liquid), close the balance valve, and then open the valve on the other side. When the equipment is shut down, the high pressure (or low pressure) valve should be closed first, then the balance valve should be opened, and then the valve should be closed on the other side. Someti
2026.07.31
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top