What factors are related to the running cycle of the air separation plant?

What factors are related to the running cycle of the air separation plant?
Oct 10, 2022
Author: DEAR AST
Question Reply

Air separation equipmentThe determination of the running cycle is mainly based on the time interval when a small amount of carbon dioxide is brought into the air separation tower and gradually accumulates until it can not continue running because of blocking. Under normal circumstances, the continuous running time of all low pressure oxygen generator should be more than one year, and the continuous running time of new molecular sieve adsorption process can be more than two years. However, in actual operation, the situation is much more complicated than the design. The main factors affecting the running cycle include the continuous working ability of the oxygen generator equipment and the running machine, the quality of heating and blowing before starting, the level of operation during the starting stage and normal operation, the size of the air load, etc.
Most of the reasons that cause the oxygen generator to be shut down and overhauled before the specified period are the failure of running machinery and switching system. It is mainly the failure of air compressor, expansion machine and liquid oxygen pump. At the same time, the internal leakage of forced Valve and automatic valve of air separation, some heat exchanger and the internal damage and internal leakage of low temperature valve, pipeline Expansion joint fatigue fracture, etc., will make the oxygen generator need to stop in the Midway for overhaul.
The heating blow-off before the start-up of the oxygen generator and the operation in the start-up stage also directly affect the operation cycle. This kind of situation often happens: due to the eagerness to produce oxygen, the heating and blowing are not complete, and the remaining water in the tower causes the resistance of the cold accumulator or the reversible heat exchanger to be too large after starting, and sometimes the resistance of the distillation tower is too large, so that liquid flooding occurs frequently. In the start-up stage, the time spent on crossing the frozen zone of water and carbon dioxide is prolonged, and the temperature difference at the cold end of the switching heat exchanger is not controlled within the allowable range (in the start-up stage, this temperature range is gradually reduced as the temperature decreases), which will cause the increase of moisture and carbon dioxide impurities brought into the air separation tower. The interruption of the start-up process of the air separation plant or the start-up for many times will cause the rise of the temperature of the cooler or the switching heat exchanger, which will bring a large amount of carbon dioxide into the tower, thus shortening the operation cycle.
In normal operation, the temperature difference control at the cold end of the switching heat exchanger is the one that has the greatest influence on the operation cycle. If the temperature is not well controlled, on one hand, it will cause the self-cleaning effect of switching heat exchanger is not good, and the resistance of carbon dioxide will rise due to accumulation in the heat exchanger; on the other hand, it will bring a small amount of carbon dioxide into the tower. Due to the impact of airflow, the actual content of carbon dioxide in the cold end air of the cooler and the switching heat exchanger will exceed the saturation content, which will also affect the operation cycle. Especially, the cold section of the switching heat exchanger is too short, and the precipitation area of carbon dioxide is shortened, which makes it easier to bring part of carbon dioxide into the tower, causing the resistance of the distillation tower to increase, the main cold heat transfer to be weakened, and the supercooler to be blocked, when the pressure of the lower tower rises, the air volume and oxygen output of the inlet Tower decrease.
Switching heat exchanger with water will also shorten the operation cycle. It is usually caused by improper operation of nitrogen-water precooler. While slight water inflow is often due to the neglect of blowing off the water separator and the emission of condensate in the air main tube of the switching heat exchanger.
The Air processing status of the air inlet sub-equipment is also an important factor affecting the operation cycle. Because the increase of air volume or inlet air temperature will increase the burden of cooling accumulator or switching heat exchanger to clear water, and increase the temperature difference of heat exchange. In the cold end, it is manifested as self-cleaning failure, and the resistance increases faster. Therefore, the operation cycle will be shortened in high-load production, while it can be extended in low-load production.
It is of great economic significance to extend the operation cycle of the air separation plant. It can reduce the standby machine, reduce the overhaul time, save money and produce more oxygen and nitrogen products. Therefore, the operation should be managed and maintained elaborately.

DEAR Air Separation Solve YourWhat factors are related to the running cycle of the air separation plant?You can also learn about otherSmall air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
The most likely leakage of switching heat exchanger is the welding line, especially the joint of the head and the pipeline. Most of the causes of leakage are the quality problems of manufacture and installation, which are also related to maintenance. The working condition of switching heat exchanger is poor. It is not only impacted by alternating airflow, but also changes greatly in airflow temperature. In long-term operation, the weak parts are easy to leak. Therefore, the welding quality should be strictly guaranteed during manufacture and installation. After installation, strict leak detection and pressure test must be carried out before driving, and problems should be dealt with timely to avoid passivity after driving. There are three methods to check whether the switching heat exchanger leaks in operation: 1) flow method. When a large amount of leakage occurs between the channel of product oxygen or product nitrogen and air channel, the output of oxygen or nitrogen increases ob...
2024.03.29
Oxygen product: liquid oxygen is pumped out from the lower tower plate of the low pressure tower and sent to the storage tank, the inner compressed oxygen pump is placed next to the liquid oxygen storage tank, the liquid oxygen extracted from the storage tank is pressurized by the oxygen pump and sent out after gasification and reheating in the main heat exchanger to get the required oxygen product in liquid air separation plant. The nitrogen product is pumped from the top of the pressure tower...
2024.03.28
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top