News on May 15, learned from the person in charge of the equipment manufacturer:
The production schedule of the 30 thousand air separation project supplied by DEAR air separation to Anfeng Iron and Steel Group is in progress according to the requirements of the contract. Part of the completed production equipment has passed the factory inspection, which meets the delivery standard and is ready to be delivered.
The production and production of the main equipment provided by DEAR air separation for Hebei Sanhe heavy industry project have all been completed, passed the factory inspection and met the delivery standard, and have been sent to the site now.
III. Project
Anfeng project
Anfeng project