当前位置: Home / Faq / Small air separation FAQ /

How to perform bare cooling on air separation equipment and what work needs to be done after bare cooling

How to perform bare cooling on air separation equipment and what work needs to be done after bare cooling
Jun 28, 2023
Author: DEAR AST

In bare cooling, the main equipment such as the distillation tower and main condenser evaporator should be sequentially cooled to the lowest temperature for 2 hours each. Then cool the entire air separation equipment until it reaches equilibrium temperature, so that all equipment pipelines have white frost on their surfaces, and maintain it for 3-4 hours.

In the cold state, each part should be carefully inspected for deformation and leakage. The location of the leakage point can be determined based on the frost formation and should be marked. After freezing, the flange screws should be tightened again to compensate for the screw relaxation caused by different thermal expansion coefficients at low temperatures. But it should also be noted not to tighten too tightly to prevent excessive prestressing. Then sweep the frost and avoid melting it in the insulation box, which may affect the filling of the insulation material. Heat it again to room temperature and conduct an air tightness test.

If there are any treatment items, they need to be exposed again after treatment. The number of times and qualification standards for bare cooling depend on the specific situation. After the bare cooling is qualified, each adsorber is loaded with adsorbent, and the cold insulation box is filled with cold insulation materials.

DEAR Air Separation is a professional research and development, manufacturing, and installation of various complete sets of air separation equipment. With unique design and insights into air separation industry solutions, we provide customers with safe and reliable products.

DEAR Air Separation Solve YourHow to perform bare cooling on air separation equipment and what work needs to be done after bare coolingYou can also learn about otherSmall air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
The air cooling tower is the core equipment of the air separation precooling system, which is mainly used to cool and wash the high-temperature compressed air discharged from the air compressor, provide qualified low-temperature gas source for subsequent molecular sieve purification and cold box rectification, and ensure the stable operation of the whole unit. The air cooling tower adopts the countercurrent packing heat exchange structure, the tower is filled with high-efficiency packing, and the top is equipped with a spray device and a wire mesh demister. During operation, the high-temperature compressed air at 80 to 100 ℃ discharged by the air compressor enters from the bottom of the tower and flows from bottom to top; The cooling water is the normal temperature make-up water and the low-temperature chilled water prepared by the water-cooling tower, which is sprayed from top to bottom from the tower top, and the air and water are fully contacted in reverse for heat exchange. Under t
2026.11.12
Regulation of liquid nitrogen throttle valveThe opening of the liquid nitrogen throttle valve not only affects the reflux ratio of the upper tower, but also affects the reflux ratio of the lower tower. When the opening is increased, the reflux ratio of the upper tower increases, while the reflux ratio of the lower tower decreases, the purity of the nitrogen in the upper tower increases, and the purity of the oxygen enriched night sky in the lower tower increases. However, after the opening is over, the purity of the liquid nitrogen decreases, and the reduction of the reflux ratio of the upper tower is also detrimental to the improvement of the purity of the liquid oxygen. Therefore, an equilibrium point should be found for the opening of the liquid nitrogen throttle valve. We can generally use the purity difference between liquid nitrogen and gas nitrogen to judge whether the opening is appropriate. Generally, the purity of the sprayed liquid nitrogen is equal to that of the upper towe
2026.11.11
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top