(1) Scale and corrosion inhibitor pouring method: according to the amount of the agent will be poured into the washed dosing bucket, in constant stirring pouring supplemental water will be diluted about 3 ~ 5 times. Dilute the agent in order to prolong the total time of pouring, according to the situation of water quality to decide whether to dilute. After mixing and stirring the drug and water, turn on the dosing pump and adjust the dosing valve so that the drug is continuously and evenly poured into the catch basin, and ensure that the pouring is completed within 20~24 hours.
(2) Algaecide dumping method: proportionally dump the agent directly into the catch basin, the circulating water can maintain a certain concentration of the agent for a period of time is to ensure effective killing and stripping of algae.
Precautions
(1) The water treatment chemicals should be stacked neatly in the storage room according to the brand number to avoid confusion and misuse of chemicals.
(2) According to the water quality test results (concentration multiplier, turbidity total phosphorus) and circulating water control index, drain, replace or dump the medicine as required.
(3) Staff should wear protections when carrying out dumping operations to avoid direct contact between the agent and the skin and eyes. If the agent inadvertently comes into contact with the skin, it should be rinsed off immediately with plenty of water.
(4) The method of adding water treatment chemicals needs to be carried out in strict accordance with the relevant requirements and to do a good job of safe production.
Dear air separation advanced technology, scientific management, intelligent manufacturing process strongly ensure that our small air separation unit, large air separation unit and liquid air separation plant design and manufacturing industry's leading position.