Cold test of large air separation unit

Cold test of large air separation unit
Mar 23, 2022
Author: DEAR AST

1. Before the overall large air separation unit cold test. Fractionation should be fully heated and blown out. Air turbine compressor, turbine expander, air pre-cooling system, molecular sieve purification system and electrical, instrumentation and control system must be ready for operation.

2、The operation of the cold test is carried out in accordance with the operating instructions of the large air separation unit, in order to cool the distillation tower, the main condenser and other major large air separation unit to as low a temperature as possible, fighting all the containers in the cold box, the outer surface of the pipeline frost, and should be maintained for at least 2 hours.

3. In the cold test process, personnel should be organized to enter the cold box must wear cold hats, gloves, cotton clothing, etc. Strictly check the leakage parts and make marks. For cold valve, low temperature film adjustment valve can be used to tighten the nut with special tools. And should pay attention to the valve is not stuck phenomenon, cold test is over, but also natural reheat, as long as the cold box manhole cover can be opened, should be airtight test, but also dynamic test, so all the bolts, flange connections, valves and other parts shall be tightened once. To pay special attention to the tightening of the valve can not be completely closed state.

4. The overall cold test of large air separation unitshould generally be carried out twice, according to the test leakage and treatment.

江苏-善俊

 

DEAR Air Separation Solve YourCold test of large air separation unitYou can also learn about otherLarge air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
Why do the design, installation, and production of complete sets of air separation equipment require various parameters from the demand side?
2024.11.14
The classical single column process is the first one to be used in industrial application. However, there are many disadvantages in the classical single column process. One is that oxygen and nitrogen cannot be produced simultaneously, and the other is that the oxygen extraction rate can only reach about 70%. There are two improvement schemes to solve the defects of classical single column process. One is the curren...
2024.11.13
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top