Cold test of large air separation unit

Cold test of large air separation unit
Mar 23, 2022
Author: DEAR AST

1. Before the overall large air separation unit cold test. Fractionation should be fully heated and blown out. Air turbine compressor, turbine expander, air pre-cooling system, molecular sieve purification system and electrical, instrumentation and control system must be ready for operation.

2、The operation of the cold test is carried out in accordance with the operating instructions of the large air separation unit, in order to cool the distillation tower, the main condenser and other major large air separation unit to as low a temperature as possible, fighting all the containers in the cold box, the outer surface of the pipeline frost, and should be maintained for at least 2 hours.

3. In the cold test process, personnel should be organized to enter the cold box must wear cold hats, gloves, cotton clothing, etc. Strictly check the leakage parts and make marks. For cold valve, low temperature film adjustment valve can be used to tighten the nut with special tools. And should pay attention to the valve is not stuck phenomenon, cold test is over, but also natural reheat, as long as the cold box manhole cover can be opened, should be airtight test, but also dynamic test, so all the bolts, flange connections, valves and other parts shall be tightened once. To pay special attention to the tightening of the valve can not be completely closed state.

4. The overall cold test of large air separation unitshould generally be carried out twice, according to the test leakage and treatment.

江苏-善俊

 

DEAR Air Separation Solve YourCold test of large air separation unitYou can also learn about otherLarge air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
In the liquid air separation plant, the cooled refrigerant goes to the air machine through the refrigerant delivery pipeline, and the intercooler cools the compressed air to around 10°C, improving the efficiency of the air compressor and reducing the energy consumption of the air compressor. The air separation unit uses circulating nitrogen to recycle and utilise the CNG cold through a heat exchanger, which in turn liquefies the air to transfer the cold to the liquid air separation plant, an...
2026.03.31
The plant operation cycle between two large heating is related to many factors. From an operational point of view, this mainly depends on when the air passage of the main heat exchanger is blocked. The main reason for the blockage is that the moisture and carbon dioxide content in the air entering the unit exceeds the standard, which accumulates and freezes in the main heat exchanger until it is blocked. The abnormal operation of molecular sieve purification system will shorten the operation cycle of the unit. It is mainly caused by the following reasons: 1. The molecular sieve adsorption bed is short circuited. In the process of operation, due to the unstable gas velocity control or switching, the pressure difference between the two tanks is too large, which will affect the bed layer, make the molecular sieve bed uneven and make the bed layer short circuit. In serious cases, the dust screen of the adsorber will break and the molecular sieve powder will enter the heat exchanger c
2026.03.30
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top