Cold test of large air separation unit

Cold test of large air separation unit
Mar 23, 2022
Author: DEAR AST

1. Before the overall large air separation unit cold test. Fractionation should be fully heated and blown out. Air turbine compressor, turbine expander, air pre-cooling system, molecular sieve purification system and electrical, instrumentation and control system must be ready for operation.

2、The operation of the cold test is carried out in accordance with the operating instructions of the large air separation unit, in order to cool the distillation tower, the main condenser and other major large air separation unit to as low a temperature as possible, fighting all the containers in the cold box, the outer surface of the pipeline frost, and should be maintained for at least 2 hours.

3. In the cold test process, personnel should be organized to enter the cold box must wear cold hats, gloves, cotton clothing, etc. Strictly check the leakage parts and make marks. For cold valve, low temperature film adjustment valve can be used to tighten the nut with special tools. And should pay attention to the valve is not stuck phenomenon, cold test is over, but also natural reheat, as long as the cold box manhole cover can be opened, should be airtight test, but also dynamic test, so all the bolts, flange connections, valves and other parts shall be tightened once. To pay special attention to the tightening of the valve can not be completely closed state.

4. The overall cold test of large air separation unitshould generally be carried out twice, according to the test leakage and treatment.

江苏-善俊

 

DEAR Air Separation Solve YourCold test of large air separation unitYou can also learn about otherLarge air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
The molecular sieve used in oxygen generators is the zeolite molecular sieve. It is a crystalline silica and aluminate polyhydric compound. Molecular sieves have a uniform pore size and their main function is to sieve molecules. There are three main types of molecular sieves: A, X and Y. The 13X molecular sieve is the only adsorbent currently used in liquid air separation plants. Any molecules that can be adsorbed on 3A, 4A and 5A molecular sieves can be adsorbed by 13X molecular sieves. It is c...
2026.09.30
Pressure test before valve installation 1. In the warranty period, those with the certification and the sealing surface is intact can no longer conduct the strength test alone, but only the air tightness test can be taken before installation. 2. Within the warranty period, it has the certificate, and its sealing surface has defects such as corrosion and damage. After treatment, it must carry out the air tightness test. 3. Outside the warranty period, those with certification and intact sealing surface shall be subject to air tightness test before installation. 4. For valves that need to be degreased and disassembled on site, air tightness test shall be conducted separately before installation. 5. The safety valve shall be sent to the local quality inspection department of the project for verification before the end of installation and commissioning.
2026.09.29
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top