Cold test of large air separation unit

Cold test of large air separation unit
Mar 23, 2022
Author: DEAR AST

1. Before the overall large air separation unit cold test. Fractionation should be fully heated and blown out. Air turbine compressor, turbine expander, air pre-cooling system, molecular sieve purification system and electrical, instrumentation and control system must be ready for operation.

2、The operation of the cold test is carried out in accordance with the operating instructions of the large air separation unit, in order to cool the distillation tower, the main condenser and other major large air separation unit to as low a temperature as possible, fighting all the containers in the cold box, the outer surface of the pipeline frost, and should be maintained for at least 2 hours.

3. In the cold test process, personnel should be organized to enter the cold box must wear cold hats, gloves, cotton clothing, etc. Strictly check the leakage parts and make marks. For cold valve, low temperature film adjustment valve can be used to tighten the nut with special tools. And should pay attention to the valve is not stuck phenomenon, cold test is over, but also natural reheat, as long as the cold box manhole cover can be opened, should be airtight test, but also dynamic test, so all the bolts, flange connections, valves and other parts shall be tightened once. To pay special attention to the tightening of the valve can not be completely closed state.

4. The overall cold test of large air separation unitshould generally be carried out twice, according to the test leakage and treatment.

江苏-善俊

 

DEAR Air Separation Solve YourCold test of large air separation unitYou can also learn about otherLarge air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
What are the requirements for selecting materials for high purity nitrogen gas distribution pipelines in small air separation unit?   High purity nitrogen gas has to be transported through pipelines to the point of use of the small air separation unit. In order to meet the quality requirements of the gas for the process, the selection of materials for the piping system and the quality of construction need to be paid more attention to during the construction process, provided that the gas ...
2026.07.09
Liquid air separation plant solutions Most liquid air separation plant cold energy receiving stations have a peaking role, their use is generally for domestic gas or car refuelling, with high and intermittent periods of gas consumption, for example 1-2 hour peaks in the morning and midnight. If the liquid air separation plant vapourisation plant is intermittent, the plant will not operate continuously. The solution is based on the intermittent use of liquid air separation plant and is character...
2026.07.08
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top