Installation of the air pre-cooling system in small air separation unit

Installation of the air pre-cooling system in small air separation unit
Mar 16, 2022
Author: DEAR AST

Installation of the air pre-cooling system in small air separation unit

(1) Air cooling tower is a pressure vessel, the site is strictly prohibited on the tower body fire.

(2) installation requirements: verticality <1/1000, the full length of the range shall not exceed 10mm.

(3) loading material before, clear the tower debris and check the tower pieces of fasteners, confirm no loose, off.

(4) bare cold before, air-cooled tower, water-cooled tower at the top of the screen mist trap again check, confirm no gap, no loose.

(5) filler into the tower before, need to check the filler specifications, apparent quality, strength, quantity, etc. to confirm the correct. If the filler can not be filled immediately, need to be stored in the warehouse, should not be long-term open-air placement.

(6) filler installation: filler shall not be mixed, shall not contact grease. Can not be directly from the top of the tower directly into, should be from different heights of the hole for layering filling.

(7) test pressure: after installation, to work pressure on the system for gas tightness test, maintain pressure time shall not be less than 2 hours, shall not leak.

Dear Air Separation manufactures full set of small air separation units and large air separation units including air pre-cooling systems.

山东传洋集团20000

 

DEAR Air Separation Solve YourInstallation of the air pre-cooling system in small air separation unitYou can also learn about otherSmall air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
Liquid air separation plant cold energy utilises air separation equipment, generally large air separation equipment with 2 combined expanders. The price is around 4 million RMB. The expansion air in the air separation plant is no longer required, so for the internal compression process air separation, the inlet air volume of the circulating booster is reduced by about 40% (from 5.A-2A). The energy consumption of the booster is reduced and the investment is reduced. Liquid air separation equipmen...
2026.06.18
1.In the process of preparation and implementation of hoisting construction, the safety and quality assurance system must ensure the normal operation,to ensure that the hoisting project meets the requirements of safety and quality. Before hoisting, safety and quality inspection must be carried out, and it must comply with the code forLifting construction of chemical engineering construction (HG20201-2000) and other regulations and specifications. 2.The crane performance shall meet the requirements of hoisting process, and the alarm and hydraulic system must be reliable. 3.Strictly implement the provisions of the technical documents attached to the crane. 4.The hoisting schedule of auxiliary crane should match that of main crane. 5.The hook deflection angle shall not be greater than 3°. 6.It is forbidden to drag the unitdirectly on the ground with crane. 7.Before unithoisting, trial hoisting shall be carried out. The clear hoisting distance and the foundation change at
2026.06.17
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top