A low pressure nitrogen expander is added to the process design. The pressure nitrogen from the pressure tower and high pressure expander is expanded into low pressure nitrogen, which is combined with the nitrogen coming from the low pressure tower and fed into the charge gas compressor. This is specially set up for rapid oxygen load changes. The oxygen product flow rate during normal operation corresponds to the amount of oxygen contained in the amount of air entering the air separation unit. That is, the amount of liquid oxygen pumped from the low pressure tower into the storage tank is the same as the amount of liquid oxygen extracted from the storage tank and pressurized by the liquid oxygen pump to the main heat exchanger of liquid air separation plant.

With this nitrogen cycle rapid load change technology, compared with the conventional air booster internal compression process, it is not only possible to meet a large range of rapid oxygen production changes without bypass or additional compressors, but also to minimize the impact of compressor flow and pressure changes on the distillation column caused by a wide range of variable loads. The working condition in the distillation tower remains basically unchanged when the oxygen output varies from ±20,000Nm3/h at the operating point.

上海宝冶集团有限公司-7500

DEAR Air Separation Solve YourFast Variable Load Technology of Liquid Air Separation PlantYou can also learn about otherLiquefied air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
What is the enthalpy in the air separation plant?
2026.08.20
1. Before filling with pearlite, the water accumulated on the foundation surface of air separation unit must be removed, dried with hot air, and all manholes shall be closed. 2. When filling pearlite, all containers and pipes in the cold box should be inflated and kept at 50kPa pressure, then slightly open the valve of each meter pipeline, and all thermometers should be electrified to check whether the thermometer cable is damaged during the filling process. 3. The filled pearlite shall not be mixed with combustibles. 4. When filling with pearlite, coarse mesh or pearlite pouring device should be set at the manhole on the top of the cold box to prevent whole bag pearlite from entering the cold box. 5. After the pearlite is filled, the manhole shall be sealed.
2026.08.18
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top