Question Reply

In the air separation unit of molecular sieve adsorption purification process, after the air is compressed at the last stage of the air compressor, the temperature out of the air compressor reaches 80-90 ℃. Since the adsorption capacity of molecular sieve is inversely proportional to the temperature, in order to improve the working efficiency of molecular sieve adsorber and ensure the purification effect, the compressed air from the air compressor must be cooled to reduce the temperature of the compressed air before entering the purification system.

 

The pre cooling system is composed of water chiller, water cooling column, air cooling column, cooling chilled water pump, water filter, etc. the pre cooling system must have enough cold source to cool the air. The heat exchange device is used to realize the heat exchange between the air and the cold source. The water separator separates the water when the temperature drops, so as to ensure that the dry air enters the purification system.

 

1.In the air cooling column, the cooling water and compressed air exchange heat through direct contact between gas and liquid. There are two sources of cooling water, onepartis the normal temperature water of the water cooling column, which is cooled by sewage nitrogen, after the temperature is reduced, the water is supplied to the air cooling column by water pump, and the other one part is the chilled water provided by the chiller.

 

2.After the air is cooled to 40 ℃ by the end cooler of the compressor, the air enters the evaporator of the refrigerator. The air is directly cooled by the evaporation heat absorption of the refrigerator without indirect cooling by chilled water.

 

3.The manufacturers with surplus crudenitrogen can make full use of the heat absorption potential of the crudenitrogen discharged from the cooling box, absorb the latent heat of evaporation of water in the water cooling column, reduce the temperature of the cooling water, and then enter the air cooling column to cool the air.

 

4.When the pressure swing adsorption regeneration purification system is used, the air temperature is required to be less than 40 ℃. At this time, the design margin of the aftercooler can be larger, and then the air can be directly cooled to 37 ℃ by the aftercooler.

DEAR Air Separation Solve YourHeat exchange form of precooling system in air separation unitYou can also learn about otherLarge air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
The comprehensive energy-saving transformation of cryogenic air separation is not a single point of equipment replacement, but a collaborative optimization of the whole system, which mainly covers six technical sectors: 1. optimization of compressed air supply system: frequency conversion/permanent magnet transformation of air compressor, matching of air supply pressure, reducing the loss of venting and depressurization, solving the problem of "big horse pulling small car", and the compression link accounts for more than 70% of the total energy consumption of air separation, which is the focus of energy conservation; 2. transformation of precooling and purification system: high efficiency and low resistance molecular sieve, adaptive regeneration control, air inlet precooling, reduce regeneration energy consumption and system resistance, and reduce compressor load; 3. upgrading of rectification and main heat exchange system: efficient and regular packing, optimization of reflux ratio, o
2026.11.20
Answer:>>the conventional air separation unit of DEAR air separation plant is designed for 20 years, which meets the design service life recommended by national standards and specifications, and is also the cost-effective optimization scheme for bot/boo gas investment and long-term stable gas consumption projects. The default recommended design service life of the national standard and relevant specifications, feasibility study, bidding and preliminary design drawings of pressure vessels is 20 years. Designed for 20 years: the cold box plate, heat exchanger and pressure bearing parts are of higher material selection grade, suitable for long-term continuous operation, and suitable for bot/boo gas investment, metallurgy and chemical industry long-term gas supply projects; The maintenance is in place and the technical transformation is timely. The actual stable service can reach 20-25 years, and the working condition management can reach 28-30 years. 15 years of design: moderate investmen
2026.11.20
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top