1.Before hoisting, check and confirm whether the crane body, crane legs, lifting rigging and wire rope meet the safety requirements and hoisting conditions.

 

2.The hanging points of hoisting facilities shall be confirmed to prevent deviation and inclination; steel wire rope or sling shall be used for protection of edges and corners; sling and U-ring shall be used for lifting objects.

 

3.The commander shall use inter-phonefor command, and special personnel shall be assigned for command, and the personnel shall stand at the position where the lifting object can be fully observed; warning isolation shall be set up in the hoisting area, and no one shall stand under the lifting object.

 

4.For large-scale hoisting, the hoisting safety scheme shall be formulated in combination with the company's special operation system.

DEAR Air Separation Solve YourSafety measures for hoisting operation of air separation plantYou can also learn about otherLarge air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
Pressure swing adsorption and temperature swing adsorption of molecular sieve
2024.12.19
What is the function of the distillation tower in air separation equipment?
2024.12.18
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top