What should be done when the power supply of the air separation plant of the molecular sieve adsorption purification process is restored after the power failure?

What should be done when the power supply of the air separation plant of the molecular sieve adsorption purification process is restored after the power failure?
Oct 10, 2024
Author: DEAR AST
Question Reply

Molecular sieve adsorption purification processAir separation equipmentWhen the power supply is restored after the power failure, the operation should follow the following steps:
1) judge the possible influence on mechanical equipment such as air compressor when the power is suddenly cut off. If there is no influence, according to the operation specification of the air compressorAir compressorStart-up preparation;
2) check and confirm the switch state of the chain shutdown equipment valve;
3) check and confirm the alarm chain project of the air separation plant. Re-check and confirm the chain control of failure during power failure;
4) start the air compressor and air precooling system according to regulations;
5) start the molecular sieve adsorber according to the regulations. Continue to complete the process before shutdown. If the downtime is long (more than 24 h), the molecular sieve adsorber should recycle for one cycle;
6) according to the length of downtime, the cold end temperature of the main heat exchanger and the main cold liquid level, etc., according to the regulations to determineAir separation equipmentStart the startup procedure.

DEAR Air Separation Solve YourWhat should be done when the power supply of the air separation plant of the molecular sieve adsorption purification process is restored after the power failure?You can also learn about otherAir separation parts FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
Where is the refrigeration capacity generated by the air separation plant mainly consumed?
2026.09.07
According to the daily water quality analysis and laboratory results, supplement the discharge water and control the dosing amount to make it reach the required data index. When the turbidity is >20mgL, increase the amount of drainage water, increase the flow of side filtration, and supplement clean water. According to the current situation of the circulating water system, try to increase the concentration multiple operation to save water and medicine. If the concentration multiplier is g...
2026.09.04
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top