How to operate small air separation plant when the low temperature thermometer fails?

How to operate small air separation plant when the low temperature thermometer fails?
Feb 19, 2024
Author: DEAR AST
Question Reply

Kong fen taThe three-point temperature of low temperature meter is: T3 temperature refers to the temperature before high pressure air throttling; T2 temperature refers to the temperature of air after expansion; T1 refers to the temperature after the first heat exchanger and before the expansion machine. The function of the three-point temperature is mainly to control the gas distribution between the expansion machine and the joint-1 valve during the start-up stage of the air separation tower. There is no need to control the normal and stable operation. If only one or two of the thermometer is out of order, we can speculate the working condition according to the intact temperature point. When the three-point temperature is completely out of order, it can be operated according to the temperature difference between the Heat end of the heat exchanger (namely the temperature difference between the air inlet device of processing air and the outlet temperature of oxygen, nitrogen and distillation, make the temperature difference of the hot end not greater than the normal value.
If the temperature difference of the hot end is in the normal value, try to turn on the cam mechanism as large as possible and turn off the small high pressure air throttle accordingly. When the cam mechanism has been opened to the maximum air intake position, the joint-1 valve can be used to adjust according to the need of liquid oxygen level. If the temperature difference of the hot end is greater than the normal value, open the big section-1 valve and close the small cam mechanism. In this case, the operation should be predictable, and the delayed reaction should be paid attention.
Because the change of temperature difference at the Heat end of the heat exchanger is the result of the internal temperature change of the first and second heat exchanger. When passingExpanderWhen the air is too much, the air volume passing through the joint-1 valve decreases correspondingly, the positive flow air of the second heat exchanger decreases, while the amount of oxygen and nitrogen flowing back remains unchanged, and the function of the second heat exchanger is not fully exerted. On the contrary, the load of the first heat exchanger increases, the cold recovery of the return gas is not perfect, and the temperature difference of the Heat end is enlarged. When starting, the liquid oxygen level is not easy to rise, and when depressurizing, it cannot depressurize. When the temperature difference of the original hot end is relatively large, after adjusting the opening degree of the joint-1 valve and Cam, and the temperature difference of the hot end is close to the normal value, it should be carefully and slowly stabilized. The operation without low thermometer indication depends entirely on personal experience, and the previous operation records can be used as reference.

DEAR Air Separation Solve YourHow to operate small air separation plant when the low temperature thermometer fails?You can also learn about otherSmall air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
Liquid air separation plant cold energy utilises air separation equipment, generally large air separation equipment with 2 combined expanders. The price is around 4 million RMB. The expansion air in the air separation plant is no longer required, so for the internal compression process air separation, the inlet air volume of the circulating booster is reduced by about 40% (from 5.A-2A). The energy consumption of the booster is reduced and the investment is reduced. Liquid air separation equipmen...
2026.06.18
1.In the process of preparation and implementation of hoisting construction, the safety and quality assurance system must ensure the normal operation,to ensure that the hoisting project meets the requirements of safety and quality. Before hoisting, safety and quality inspection must be carried out, and it must comply with the code forLifting construction of chemical engineering construction (HG20201-2000) and other regulations and specifications. 2.The crane performance shall meet the requirements of hoisting process, and the alarm and hydraulic system must be reliable. 3.Strictly implement the provisions of the technical documents attached to the crane. 4.The hoisting schedule of auxiliary crane should match that of main crane. 5.The hook deflection angle shall not be greater than 3°. 6.It is forbidden to drag the unitdirectly on the ground with crane. 7.Before unithoisting, trial hoisting shall be carried out. The clear hoisting distance and the foundation change at
2026.06.17
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top