One-week project progress (2012.8.27 -- 2012.9.2)

One-week project progress (2012.8.27 -- 2012.9.2)
Aug 27, 2012
Author: DEAR AST

One-week project progress --- Minyuan 15000 project
● Minyuan KDON (Ar)-15000/15000-500 complete set of air separation engineering project supporting main cooling has entered the installation phase of plate heat exchanger unit, which is expected to be completed in early September; the lower tower has been completed, waiting to be compounded with the main cold; the upper tower cylinder has been finished, and the docking and welding work will be completed within this week.
● The internal parts of the molecular sieve adsorber of Minyuan 15000 project are being assembled and are expected to be completed in early September.



One-week project progress --- Shangu 36000 project
● Design and Research Institute of the company signed 36000 m with Xi'an Shangu Power Co., Ltd.3/H air separation plant supply contract the design of relevant equipment drawings is completed, and the final preparation work before the review meeting is being done.



One-week project progress --- Guangxi Chuangui gas 7500 project
● Guangxi Chuangui KDON (Ar)-7500/15000/230 complete air separation project supporting oxygen compressor equipment will be delivered around September 7.

 



 

DEAR Air Separation provides you withOne-week project progress (2012.8.27 -- 2012.9.2), so you can fully understand the latest developments of DEAR Air Separation and the interpretation of DEAR News.
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top