One-week project progress --- Minyuan 15000 project
● Minyuan KDON (Ar)-15000/15000-500 complete set of air separation engineering project supporting main cooling has entered the installation phase of plate heat exchanger unit, which is expected to be completed in early September; the lower tower has been completed, waiting to be compounded with the main cold; the upper tower cylinder has been finished, and the docking and welding work will be completed within this week.
● The internal parts of the molecular sieve adsorber of Minyuan 15000 project are being assembled and are expected to be completed in early September.
One-week project progress --- Shangu 36000 project
● Design and Research Institute of the company signed 36000 m with Xi'an Shangu Power Co., Ltd.3/H air separation plant supply contract the design of relevant equipment drawings is completed, and the final preparation work before the review meeting is being done.
One-week project progress --- Guangxi Chuangui gas 7500 project
● Guangxi Chuangui KDON (Ar)-7500/15000/230 complete air separation project supporting oxygen compressor equipment will be delivered around September 7.