One-week project progress --- 1500 project of exporting to Burma
● Burma iron and steel company KDON (Ar)-1500 40Y/1500/40 Y type complete air separation engineering project supporting oxygen compressor equipment has completed the relevant pressure test piping work, entering the stage of equipment painting, is expected to be delivered around 18th day of this month.
● Burma project supporting distillation column system, purification system and other storage equipment, the client will carry out the inspection work formally on 8th day of this month, and it is expected that all inspection work will be completed before and after 15th day of this month, then carry out the shipment preparation before sending to the port.
One-week project progress --- Minyuan 15000 project
● Jinan Iron and Steel Group Minyuan Iron and Steel Co., Ltd. KDON (Ar)-15000/15000-500 complete set of air separation engineering project supporting relevant argon Tower, Tower equipment is manufactured by the plate welding plant; the production of the main Cold cylinder is completed, and it enters the Plate-fin installation stage after shooting, which is expected to be completed in early September; the assembly work of the tube body of the lower tower has been completed, and the pressing ring is being welded, which is expected to be completed by the end of September; purification system the process pipeline in the cold box has been cut off.
● The container branch plant will complete that the auxiliary molecular sieve adsorber of Minyuan 15000 project is being assembled and is expected to be completed in early September; meanwhile, the auxiliary air cooling tower equipment of this project is expected to be completed in early September.
One-week project progress --- Linyi 10000 project
● The Design and Research Institute of the company is in charge of the design work of the equipment drawings of the seventh set of KDON-10000/10000 air separation project signed by Shandong Linyi Sande Special Steel Co., Ltd., which has been completed and is being audited by relevant leaders.
One-week project progress --- Shangu 36000 project
● Design and Research Institute of the company signed 36000 m with Xi'an Shangu Power Co., Ltd.3/H supply contract of air separation plant carry out design work of relevant equipment drawings is currently in intense progress, and the preliminary drawing design is expected to be completed next week.