The internal structure of the cold box of the air separation equipment is precise and complex, which is the core area of air separation and mainly consists of the following parts:
Heat exchange system
With plate-fin heat exchanger as the core, multi-layer aluminum fins and partition plates are arranged alternately to form an independent flow path. Indirect heat exchange is conducted between feed air and reflux gas (such as pure nitrogen and polluted nitrogen) here to realize the deep cooling of air from normal temperature to - 170 ℃, and recover the cooling capacity to reduce energy consumption. Its compact structure significantly improves the heat transfer efficiency and adapts to the limited space in the cold box.
Rectification system
Including upper and lower double-column structure (HP column and LP column) and argon fractionator (large unit). High-efficiency structured packing or tray is filled in the column, and high-purity separation is realized by the difference of boiling points of oxygen and nitrogen through countercurrent contact of vapor and liquid phases. The condensing evaporators are located at the top of the column and condense gaseous nitrogen into liquid nitrogen, while vaporizing liquid oxygen to provide rising steam to maintain the rectification cycle.
Refrigeration system
Expander is a key equipment, which generates low-temperature cooling capacity through adiabatic expansion of high-pressure gas to provide continuous refrigeration for the rectifying column. Its rotating speed and inlet and outlet pressure are accurately adjusted to ensure the matching of cooling capacity and system load.
Liquid storage and transportation system
Liquid oxygen pump, liquid nitrogen pump and storage tank are used to store and transfer liquid products. The storage tank adopts pearlite cold insulation structure to reduce the loss of cooling capacity.
Piping and Valves
Low-temperature pipes shall be made of stainless steel or aluminum alloy, and connected with equipment to form a closed circulation system. Valves (such as low temperature stop valves and control valves) shall have low temperature resistance and reliable sealing characteristics to ensure stable operation of the process.

DEAR Air Separation Solve YourWhat are the internal structures of the cold box of the air separation equipment?You can also learn about otherAir separation parts FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
Liquid air separation plant cold energy utilises air separation equipment, generally large air separation equipment with 2 combined expanders. The price is around 4 million RMB. The expansion air in the air separation plant is no longer required, so for the internal compression process air separation, the inlet air volume of the circulating booster is reduced by about 40% (from 5.A-2A). The energy consumption of the booster is reduced and the investment is reduced. Liquid air separation equipmen...
2026.06.18
1.In the process of preparation and implementation of hoisting construction, the safety and quality assurance system must ensure the normal operation,to ensure that the hoisting project meets the requirements of safety and quality. Before hoisting, safety and quality inspection must be carried out, and it must comply with the code forLifting construction of chemical engineering construction (HG20201-2000) and other regulations and specifications. 2.The crane performance shall meet the requirements of hoisting process, and the alarm and hydraulic system must be reliable. 3.Strictly implement the provisions of the technical documents attached to the crane. 4.The hoisting schedule of auxiliary crane should match that of main crane. 5.The hook deflection angle shall not be greater than 3°. 6.It is forbidden to drag the unitdirectly on the ground with crane. 7.Before unithoisting, trial hoisting shall be carried out. The clear hoisting distance and the foundation change at
2026.06.17
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top