Installation of small air separation unit valves

Installation of small air separation unit valves
Dec 17, 2025
Author: DEAR AST

1 pay attention to the direction of the arrow on the valve and the process requirements of the media flow direction, in order to avoid installation small air separation unit valves errors.

2 The pipeline connected with the valve should be thoroughly cleared of dirt, dust and other foreign mechanical impurities before installation. Prevent damage of the sealing surface of the valve.

3 The cold valve on the cold box of small air separation unit should be installed at the same time as the corresponding bracket, and the valve stem should be tilted at 15℃.

4 pipeline and body welding to close the valve first and use cooling measures, the body temperature in welding is not higher than 200 ℃, so as not to deform the valve seals, affecting the normal use of the valve.

5 switch valve installation, the shaft should be in a horizontal position, flange bolts should be evenly cross-tightened.

6 remote control valve after installation. Should strictly check whether the command signal and the valve actuator action is synchronized, whether the full open and full close position is correct, and record the opening degree command and the actual opening degree relationship of the valve.

7 after the installation of the valve opening and closing should be flexible, after the connection of the pipeline and the cold test process are to check the valve opening and closing state, there shall be no jamming phenomenon to be considered qualified. Where the cold angle valve with sleeve, low temperature pneumatic film adjustment valve, in the cold test process, need to use special tools to tighten the flange bolts.

山东传洋集团18000

DEAR Air Separation Solve YourInstallation of small air separation unit valvesYou can also learn about otherSmall air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
Liquid air separation plant cold energy utilises air separation equipment, generally large air separation equipment with 2 combined expanders. The price is around 4 million RMB. The expansion air in the air separation plant is no longer required, so for the internal compression process air separation, the inlet air volume of the circulating booster is reduced by about 40% (from 5.A-2A). The energy consumption of the booster is reduced and the investment is reduced. Liquid air separation equipmen...
2026.06.18
1.In the process of preparation and implementation of hoisting construction, the safety and quality assurance system must ensure the normal operation,to ensure that the hoisting project meets the requirements of safety and quality. Before hoisting, safety and quality inspection must be carried out, and it must comply with the code forLifting construction of chemical engineering construction (HG20201-2000) and other regulations and specifications. 2.The crane performance shall meet the requirements of hoisting process, and the alarm and hydraulic system must be reliable. 3.Strictly implement the provisions of the technical documents attached to the crane. 4.The hoisting schedule of auxiliary crane should match that of main crane. 5.The hook deflection angle shall not be greater than 3°. 6.It is forbidden to drag the unitdirectly on the ground with crane. 7.Before unithoisting, trial hoisting shall be carried out. The clear hoisting distance and the foundation change at
2026.06.17
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top