Operation and maintenance of valves in air separation equipment:

1、 Low temperature valves, valves on oxygen pipelines, and valves in contact with oxygen media must be free of oil, grease, and any other impurities. When using, maintaining, and repairing these valves, special attention should be paid to ensuring that they are not contaminated with flammable materials such as oil, grease, and wax. If they come into contact with oil, grease, etc., degreasing treatment should be carried out.

2、 Valve gaskets, sealing packing, and sealing rings must also be oil-free and grease free, and must be made of non combustible materials suitable for oxygen valves. The use of oil immersed wax and combustible materials is strictly prohibited.

3、 The visible surface of the valve stem must be kept clean, and the surface of the valve stem should be regularly coated with a lubricant suitable for oxygen valves.

4、 Check the leakage of the valve.

5、 Low temperature valves, oxygen pipelines, and valves in contact with oxygen media must be cleaned and strictly degreased before installation. The solvents used for cleaning and degreasing must also be free of oil, grease, and any other impurities, and decomposed solutions are not allowed to be used. During valve installation, all solid substances such as slag, iron oxide scale, rust, welding slag, explosives (including grease, preservatives, etc.) must be removed from all valve installation locations.

For detailed management and maintenance requirements for valves and specialized valves, please refer to the relevant valve maintenance manual for details.

DEAR Air Separation Solve YourWhat should be noted for the operation and maintenance of valves in air separation equipment?You can also learn about otherBiogas purification FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
In the process of operation, especially in the start-up and shutdown of the air separation unit, one-way force should be avoided on the instrument. During the start-up of the equipment, close the high pressure and low pressure valves firstly, then open the balance valve, and then slowly open the high pressure (or low pressure) valve, so that the measured medium can enter the positive (negative) pressure chamber of the transmitter. If the liquid is to be measured, the gas in the positive (negative) pressure chamber should be discharged from the upper vent. If the gas is measured, drain the liquid accumulated in the positive (negative) pressure chamber from the lower drain screw hole. After discharging the gas (liquid), close the balance valve, and then open the valve on the other side. When the equipment is shut down, the high pressure (or low pressure) valve should be closed first, then the balance valve should be opened, and then the valve should be closed on the other side. Someti
2026.07.31
What are the reasons why the oxygen production of air separation equipment cannot meet the target
2026.07.30
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top