What preparatory work is done before the start-up operation of the fractionation tower system of the small air separation unit?

What preparatory work is done before the start-up operation of the fractionation tower system of the small air separation unit?
May 18, 2022
Author: DEAR AST

The start-up operation of the fractionation tower of a small air separation unit is crucial. During the start-up operation, the logistics, temperature and pressure in the system change dramatically. Before the small air separation unit start-up operation must be completed before the preparation work.

1, in accordance with the requirements of the technical conditions for the installation of small air separation unit to test and test qualified.

2, air purification system switching mechanism is correct, the purifier regeneration is complete.

3, the air separation equipment sets of process flow diagrams and each subsystem, each machine process flow diagrams and equipment supply diagrams check and verify.

4, Check the electrical equipment, instruments and system lines, confirm the installation, adjustment, instrumentation and control, electrical lines are smooth.

5, All containers, equipment, valves, pipelines (including meter pipelines) in the cold box are thoroughly purged and warmed, and confirmed to be clean, dry, free of impurities and oil.

6, switching valve, safety valve, pressure reducing valve, throttle valve and other valve inspection and adjustment, flexible and reliable action.

7, cold boxes, pipes and other parts of the insulation material filling or wrapping fixed.

8、The pipeline of cooling water and lubricating oil system is unobstructed, no water leakage and oil leakage.

9、The instrumentation air system can provide the instrumentation system with dust-free, oil-free and dry instrumentation air at the prescribed pressure.

DEAR air separation manufacturing sets of small air separation units and large air separation units and liquid air separation plants, the team has technical research theory support for each division of small air separation units start-up, can accurately prepare for small air separation units and large air separation units and liquid air separation plants operation.山东传洋集团20000

DEAR Air Separation Solve YourWhat preparatory work is done before the start-up operation of the fractionation tower system of the small air separation unit?You can also learn about otherSmall air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
What are the requirements for selecting materials for high purity nitrogen gas distribution pipelines in small air separation unit?   High purity nitrogen gas has to be transported through pipelines to the point of use of the small air separation unit. In order to meet the quality requirements of the gas for the process, the selection of materials for the piping system and the quality of construction need to be paid more attention to during the construction process, provided that the gas ...
2026.07.09
Liquid air separation plant solutions Most liquid air separation plant cold energy receiving stations have a peaking role, their use is generally for domestic gas or car refuelling, with high and intermittent periods of gas consumption, for example 1-2 hour peaks in the morning and midnight. If the liquid air separation plant vapourisation plant is intermittent, the plant will not operate continuously. The solution is based on the intermittent use of liquid air separation plant and is character...
2026.07.08
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top