当前位置: Home / Faq / Small air separation FAQ /

Small air separation unit valve shell casting radiographic inspection negative assessment methods

Small air separation unit valve shell casting radiographic inspection negative assessment methods
May 05, 2022
Author: DEAR AST

(a) assessment of porosity, inclusions and other defects

According to the thickness of the test site to determine the size of the assessment frame, with the assessment frame to select the most serious defects in the detection area, the size of the defect, the different sizes of defects into different points, and then according to the number of points to assess the grade.

(ii) Assessment of shrinkage and shrinkage defects

Strips of shrinkage measured its maximum length, dendritic, feathery, spongy shrinkage measured its area, and then according to different thicknesses of different levels of the maximum amount allowed to assess the grade.

(c) Cracks (hot cracks, cold cracks) and cold partitions are all impermissible defects.

(d) the negative assessment steps first qualitative, then quantitative, and finally graded.

For the type of defects in the valve body cast steel parts and the characteristics of the valve body structure, the use of radiation detection technology. According to the oxygen valve and cryogenic valve body non-destructive testing technology requirements specified in the relevant standards, strict valve quality to ensure the safety and reliability of oxygen valves and cryogenic valves, and thus ensure the safe operation of the whole life of small air separation units, large air separation units and liquid air separation plants山东钢铁集团(壶井)16000 long cycle.

Dear Air Separation's valve housing castings are flexibly inspected using advanced technology in small air separation units, large air separation units and liquid air separation plants.

 

DEAR Air Separation Solve YourSmall air separation unit valve shell casting radiographic inspection negative assessment methodsYou can also learn about otherSmall air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
1. The removal of perlite site shall be supervised by full-time personnel and guided by professionals. The principle of who organizes, who takes responsibility shall be followed. There should be a safe passage and a warning line at the removal of perlite site, and it is strictly forbidden to enter. 2. Dry air shall be used to warm the sand during the removal and knock the cold box to remove the pearlite caking, so as to prevent equipment damage caused by falling caking. 3. The removal of perlite should be carried out in layers and sand holes should be opened at different heights of the cold box. (It can be adjusted according to the site conditions) 4. In the process of removal of perlite, always supervise the caking on the top and enter the cold box for cleaning at any time. 5. In case of severe weather such as rain, snow, strong wind or sand storm danger, the construction party and the owner shall jointly confirm that the sand stripping work shall be postponed. 6. Remov
2025.04.18
How to check if the cooling water circulation of the air separation equipment is fully connected?
2025.04.17
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top