1.Operators should adjust the discharge volume in time so that the concentration times are within the index.

2.Every week, a large amount of sewage should be discharged once. Discharge the sewage from the drainage pipe at the bottom of the tower.

3.Regularly analyse the calcium loss rate. Calcium loss rate is used to assess the system scaling situation, in general, calcium loss rate ≤ 20%.

4.Monitor the cooling water analysis once a week. Main analysis items: pH, conductivity, total phosphorus, total iron, total hardness, total alkalinity, etc. Record the daily dosing, water replenishment, drainage and chemical analysis.

5.Control index water treatment standards (international): carbon steel corrosion rate ≤ 0.125mm/a: copper corrosion rate ≤ 0.005mm/a: fouling thermal resistance ≤ 1 × 10K/W. Process control index: pH ≤ 9.2: turbidity ≤ 15.0mg/L; conductivity ≤ 2000μs/cm; total iron ≤ 1.0mg; total phosphorus ≥ 6.0mg/er: calcium loss rate ≤ 20% .

Dear Air Separation always takes science and technology as the guide, and the company has 3 research centres under the design and research institute. The company has 26 senior technical titles, 70 intermediate technical titles, and a group of highly sophisticated technical research and development talents such as doctors and masters, etc. The company has a number of design experts who enjoy a reputation in the same industry in China to ensure the technical advancement of small  air separation units, large air separation units and liquid air separation plants.

 

.

梅花项目2

DEAR Air Separation Solve YourDaily management of circulating water system in large air separation unitsYou can also learn about otherLarge air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
It should contact with the front and rear processes when the piston compressor is ready to stop, we should pay attention to the following sequence: first, cut off the gas supply slowly. In order to prevent the outlet pressure from rising after the gas supply is cut off, open the vent valve at the same time. For the oxygen compressor, the vent valve should be opened slowly, because excessive opening may produce static electricity and cause fire. Then, stop the motor. After the motor stops, turn off the circulating oil pump, grease injector motor and cooling water valve. However, there are also exception cases. For example, in case of emergency shutdown, in order to save time and prevent the accident from expanding, the power supply can be cut off immediately to stop the compressor with load.
2026.01.28
Why do gas nitrogen and liquid nitrogen coexist at the top of the distillation tower of an air separation plant
2026.01.27
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top