Cleaning and degreasing of pressure vessels, valves and piping of large air separation plant

Cleaning and degreasing of pressure vessels, valves and piping of large air separation plant
Jan 21, 2022
Author: DEAR AST

1 All pressure vessels, valves and pipelines and their piping accessories must be clean, dry and free from oil and grease before installation.

2 Degreasing of aluminium parts (pressure vessels, valves and piping) of large air separation plant is strictly prohibited by the use of carbon tetrachloride.

3 Carbon steel oxygen piping outside the cold box, valves and all other parts with oxygen, must be strictly degreased before installation and use.

4 Oxygen piping before installation and use, the residue in the piping should be blown clean with oil-free dry air or nitrogen until there is no rust, dust and other dirt. The blowing speed should be greater than 20m/s.

5 Where the surface of the parts in contact with oxygen and the residual oil in operation, the residual oil of the grease shall not exceed 125mg/m20

6 It is strictly forbidden to use oxygen to blow the pipeline.

Dear intelligent production line allows automatic scheduling of orders and automatic optimization of large air separation plant and small air separation unit and liquid air spearation plant featured with intelligent MES control system.

秦皇岛安丰钢铁有限公司-KDON(Ar)-3000070000-900型空分设备

DEAR Air Separation Solve YourCleaning and degreasing of pressure vessels, valves and piping of large air separation plantYou can also learn about otherLarge air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
In the process of operation, especially in the start-up and shutdown of the air separation unit, one-way force should be avoided on the instrument. During the start-up of the equipment, close the high pressure and low pressure valves firstly, then open the balance valve, and then slowly open the high pressure (or low pressure) valve, so that the measured medium can enter the positive (negative) pressure chamber of the transmitter. If the liquid is to be measured, the gas in the positive (negative) pressure chamber should be discharged from the upper vent. If the gas is measured, drain the liquid accumulated in the positive (negative) pressure chamber from the lower drain screw hole. After discharging the gas (liquid), close the balance valve, and then open the valve on the other side. When the equipment is shut down, the high pressure (or low pressure) valve should be closed first, then the balance valve should be opened, and then the valve should be closed on the other side. Someti
2026.07.31
What are the reasons why the oxygen production of air separation equipment cannot meet the target
2026.07.30
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top