How to operate the sudden power failure of small air separation units?

How to operate the sudden power failure of small air separation units?
Nov 21, 2024
Author: DEAR AST

In case of sudden power failure during the operation of small air separation unit, the following steps should be followed:

 

First, open the vent valve (anti surge valve) of air compressor to prevent the air compressor from surging and causing the air compressor to reverse due to air backflow;

 

Then check whether the molecular sieve adsorber switch should be interlocked to close, if not, it should be manually closed, and record the program status of molecular sieve adsorber before power failure. Expander, refrigerator, air precooling system and argon purification system shall also be shut down by interlocking, if not, manually;

 

Finally, stop the delivery of oxygen and nitrogen products, stop the output of liquid oxygen, liquid nitrogen and liquid argon, and close the water valve of air precooling system and external connection.

8

DEAR Air Separation Solve YourHow to operate the sudden power failure of small air separation units?You can also learn about otherSmall air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
1. According to the specific situation of the construction, formulate the fire protection scheme, establish and improve the fire safety system, and strictly abide by the operation rules. 2. Flammable and explosive materials such as paint and thinner shall not be stored in the project site. 3. The construction unit is not allowed to set up seasoning room in the project, and is not allowed to carry out paint allocation in the project. 4. No smoking is allowed in the construction site. A fire permit shall be issued and a special person shall be assigned to supervise the operation. 5. The operation site should be equipped with sufficient fire-fighting equipment. 6. During the construction period, the use of various open fire operations in the project shall be approved by the safety and environmental protection department of the construction unit, and sufficient fire-fighting materials and fire-fighting equipment shall be provided.
2025.01.07
What aspects of old air separation equipment currently need to be updated?
2025.01.06
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top