Requirements of air separation column for foundation

Requirements of air separation column for foundation
Nov 09, 2021
Author: DEAR AST

According to the working characteristics of the air separation column and the problems that may occur in the operation of the foundation of the air separation column, there are generally the following requirements for the foundation of the air separation column:

 

The uneven settlement of the foundation of the air separation column should be avoided as far as possible to ensure the level of the distillation tray;

 

In order to prevent the foundation from frost heaving and foundation rupture, effective cold insulation, cooling dispersion, waterproof and drainage measures should be taken;

 

And the site with high terrain, low groundwater level, good surface drainage and small frost heaving property of foundation should be selected as far as possible;

 

Inflammable and explosive materials are strictly prohibited for cold box foundation.

 

Dear’s intelligent production line not only reduces 90% of the human work, but also can carry on the lean management to the intelligent system, reduce the material cost and increase the capacity.

1

DEAR Air Separation Solve YourRequirements of air separation column for foundationYou can also learn about otherLarge air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
Liquid air separation plant cold energy utilises air separation equipment, generally large air separation equipment with 2 combined expanders. The price is around 4 million RMB. The expansion air in the air separation plant is no longer required, so for the internal compression process air separation, the inlet air volume of the circulating booster is reduced by about 40% (from 5.A-2A). The energy consumption of the booster is reduced and the investment is reduced. Liquid air separation equipmen...
2026.06.18
1.In the process of preparation and implementation of hoisting construction, the safety and quality assurance system must ensure the normal operation,to ensure that the hoisting project meets the requirements of safety and quality. Before hoisting, safety and quality inspection must be carried out, and it must comply with the code forLifting construction of chemical engineering construction (HG20201-2000) and other regulations and specifications. 2.The crane performance shall meet the requirements of hoisting process, and the alarm and hydraulic system must be reliable. 3.Strictly implement the provisions of the technical documents attached to the crane. 4.The hoisting schedule of auxiliary crane should match that of main crane. 5.The hook deflection angle shall not be greater than 3°. 6.It is forbidden to drag the unitdirectly on the ground with crane. 7.Before unithoisting, trial hoisting shall be carried out. The clear hoisting distance and the foundation change at
2026.06.17
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top