What technical requirements should be met when the pure argon tower is compounded with the condensing evaporator?

What technical requirements should be met when the pure argon tower is compounded with the condensing evaporator?
Nov 30, 2023
Author: DEAR AST
Question Reply

Pure argon Tower and the condensation evaporator composite should be met:

1.Pure argon TowerAnd condensing evaporator is manufactured, inspected and checked and accepted according to the relevant provisions of JB/T2549-1994 "aluminum air separation equipment manufacturing technical specification" and JB/T4734-2002 "Aluminum Welding container.

2. the welding joints of Class A and B of containers should be 100% x-ray tested to meet the n-level requirements of JB/T4730-2005 nondestructive testing of pressure-bearing equipment; the welding joints of class C and D should be 100% permeated tested, if the quality reaches Grade I of JB/T4730-2005, it is qualified.

3. after the compounding, Channel I (the outside of the upper part) first conducts the strength test with 0.23MPa gas, then decreases to 0.15MPa gas tightness test; Channel II (pure hydrogen Tower) conducts the strength pressure test with 0.104MPa gas, then lower the pressure to 0.08MPa to conduct air-tightness test; III channel to conduct strength test with 0.69MPa gas, then lower to 0.55MPa to conduct air-tightness test; test medium is dry and clean air or nitrogen, test procedures and requirements should be conducted according to pressure vessel safety technology supervision regulations.

4. All parts must be passivated with oil before assembling.

5. After compounding and pressure test, blow the inner and outer surfaces to remove dirt.

DEAR Air Separation Solve YourWhat technical requirements should be met when the pure argon tower is compounded with the condensing evaporator?You can also learn about otherLiquefied air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
The molecular sieve used in oxygen generators is the zeolite molecular sieve. It is a crystalline silica and aluminate polyhydric compound. Molecular sieves have a uniform pore size and their main function is to sieve molecules. There are three main types of molecular sieves: A, X and Y. The 13X molecular sieve is the only adsorbent currently used in liquid air separation plants. Any molecules that can be adsorbed on 3A, 4A and 5A molecular sieves can be adsorbed by 13X molecular sieves. It is c...
2026.09.30
Pressure test before valve installation 1. In the warranty period, those with the certification and the sealing surface is intact can no longer conduct the strength test alone, but only the air tightness test can be taken before installation. 2. Within the warranty period, it has the certificate, and its sealing surface has defects such as corrosion and damage. After treatment, it must carry out the air tightness test. 3. Outside the warranty period, those with certification and intact sealing surface shall be subject to air tightness test before installation. 4. For valves that need to be degreased and disassembled on site, air tightness test shall be conducted separately before installation. 5. The safety valve shall be sent to the local quality inspection department of the project for verification before the end of installation and commissioning.
2026.09.29
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top