One-week project progress (2012.9.24 -- 2012.9.30)
Sep 24, 2012
Author:
DEAR AST
One-week project progress --- Minyuan 15000 project
● The compound work of the lower tower and the main cooling of the matched condensing evaporator equipment of Minyuan 15000 project is in progress and is expected to be completed within this week.
One-week project progress --- Shanjun 8000 Project
● Jiangsu Shanjun KDON (Ar)-8000/2000-240 complete set of air separation project supporting oxygen evaporator equipment has been completed.