When water entrainment occurs to the air cooling tower of air separation equipment, effective measures must be taken quickly to prevent the problem from worsening and affecting the stable operation of the entire air separation system.
Once water entrainment is detected, immediately shut down the circulating water pump. This is because a continuous supply of cooling water intensifies the entrainment of water, allowing more water to be entrained by air into the subsequent system, causing greater damage to the equipment. Then, vent the air compressor to reduce the air pressure in the system and avoid more unstable factors caused by abnormal pressure. At the same time, quickly close the air inlet purifier or air inlet valve, and cut off the channels for air with water to enter the key links such as subsequent rectification to prevent water from polluting the subsequent equipment and products.
Organize professionals to carry out comprehensive inspection on the air cooling tower after the above emergency operations are completed. Focus on checking whether the filler is blocked, whether the spray nozzle is uniform, whether the demister is damaged, etc. The abnormality of these parts is often the common cause of entrainment of water. Find out the specific cause and carry out targeted treatment, such as cleaning the blocked packing, replacing the damaged nozzle or demister, etc.
When the problem is completely solved and the system is confirmed to be normal, the circulating water pump, air compressor and other equipment can be gradually restarted according to the operating procedures to restore the normal operation of the air separation system and ensure the production safety and product quality.

DEAR Air Separation Solve YourHow to operate in case of water entrainment in air cooling tower of air separation equipment?You can also learn about otherAir separation parts FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
What is the oxygen internal compression process
2026.03.27
Pipe of small air separation unit before installation, check the orientation of the container orifice, the orientation of the valve inlet and outlet is correct. The pipe fittings should be thoroughly cleaned ten net and strictly degreased, while opening the welding bevels etc. The welded pipe must be brushed with clean stainless steel wire for a very short time before welding. In order to reduce the cold box pipe welding mouth, can be prefabricated in a clean plant, and later for the final dist...
2026.03.26
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top