What are the requirements of the air separation equipment gas station for the surrounding air?

What are the requirements of the air separation equipment gas station for the surrounding air?
Dec 20, 2023
Author: DEAR AST

In order to ensure the safety of oxygen production, there are certain restrictions on the combustible impurities of hydrocarbons in the air at the suction port of the air compressor. According to GBl6912-1997 "Technical Safety Regulations for Oxygen and Related Gases", the impurity content should be lower than the allowable limit content specified in the table below.

The allowable limit content of hydrocarbons and other impurities in the air at the suction port

Names of impurities such as hydrocarbons

Permissible limit content (carbon content)/mg · m-3

There is a liquid air adsorption purification device inside the air separation tower

There is a molecular sieve adsorption purification device in front of the air separation tower

Acetylene

0.5

5

Acetylene derivatives

0.01

0.5

C5、C6saturated and unsaturated hydrocarbon impurities totaling

0.05

2

C3、C4saturated and unsaturated hydrocarbon impurities totaling

0.3

2

C2saturated and unsaturated hydrocarbon impurities total

10

10

Carbon sulfide(CS2)

Nitrogen oxide(NO)

Ozone(O3)

0.03

1.25

0.215

 

DEAR Air Separation Solve YourWhat are the requirements of the air separation equipment gas station for the surrounding air?You can also learn about otherAir separation parts FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
Liquid air separation plant cold energy utilises air separation equipment, generally large air separation equipment with 2 combined expanders. The price is around 4 million RMB. The expansion air in the air separation plant is no longer required, so for the internal compression process air separation, the inlet air volume of the circulating booster is reduced by about 40% (from 5.A-2A). The energy consumption of the booster is reduced and the investment is reduced. Liquid air separation equipmen...
2026.06.18
1.In the process of preparation and implementation of hoisting construction, the safety and quality assurance system must ensure the normal operation,to ensure that the hoisting project meets the requirements of safety and quality. Before hoisting, safety and quality inspection must be carried out, and it must comply with the code forLifting construction of chemical engineering construction (HG20201-2000) and other regulations and specifications. 2.The crane performance shall meet the requirements of hoisting process, and the alarm and hydraulic system must be reliable. 3.Strictly implement the provisions of the technical documents attached to the crane. 4.The hoisting schedule of auxiliary crane should match that of main crane. 5.The hook deflection angle shall not be greater than 3°. 6.It is forbidden to drag the unitdirectly on the ground with crane. 7.Before unithoisting, trial hoisting shall be carried out. The clear hoisting distance and the foundation change at
2026.06.17
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top