What is the difference between full heating of air separation equipment in the cold state and in the hot state, and what is the difference in the operation method?

What is the difference between full heating of air separation equipment in the cold state and in the hot state, and what is the difference in the operation method?
Jul 31, 2023
Author: DEAR AST

Full heating in the cold state is a heating operation after stopping. The main purpose is to remove the residual moisture, carbon dioxide, acetylene and other impurities, for the next cycle of long-term operation or maintenance.
Comprehensive warming in hot condition is the warming operation before driving. Its main purpose is to remove moisture and some solid impurities.
Full heating in the hot state, the temperature difference in the tower is less, generally less than 60 ℃; while the cold state heating, the temperature difference is more than 200 ℃. In order to prevent the tower inner vessel, pipeline thermal stress is too large and damage, the cold state of the full heating and the hot state of the full heating in the operating procedures are different.
The procedure of full-scale heating in cold state is shutdown - liquid discharge - static - cold blowing - heating - system blowing out. The end point of heating is the outlet temperature of the heated gas until it reaches room temperature. Under the hot state, the full heating operation procedure is divided into heating and blowing off two steps. In order to completely remove moisture to achieve the purpose of drying, the outlet temperature of the heated gas should be higher than room temperature. In order to remove the solid debris, the blowing off part of the full heating operation in the hot state is more important.
DEAR Air Separation has in-depth analysis and research on air separation equipment technology to provide customers with better design solutions for air separation projects.

DEAR Air Separation Solve YourWhat is the difference between full heating of air separation equipment in the cold state and in the hot state, and what is the difference in the operation method?You can also learn about otherAir separation parts FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
1. Workers must wear safety helmets properly when entering the construction site, because the construction site is often chaotic. Some equipment installation sites, several construction teams are working at the same time, it is impossible to completely guarantee that there are no falling objects.2. Proper use of personal protective equipment, and carefully implement safety protection measures. When working on high places, cliffs and steep slopes without protective facilities, safety belts must b...
2024.05.16
The skid mounting of equipment refers to connecting the pipelines, equipment, pumps, control cabinets, electrical instruments and other components of the complete set into a whole according to the designed process flow, and fixing them on an integral base through welding, bolting and other connection methods. Without site installation, it can be directly completed the mechanical and electrical integration installation of the whole set in the plant area, then transporting and hoisting will be convenient.
2024.05.15
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top