How to carry out naked cooling after installation or repair of air separation equipment

How to carry out naked cooling after installation or repair of air separation equipment
Sep 02, 2021
Author: DEAR AST

After the installation or repair of the air separation equipment, the overall bare cooling shall be carried out.

 

Naked cooling purpose: check the quality of installation or repair of air separation equipment; Cold deformation and compensation capacity of air separation unit under low temperature; Whether the equipment pipeline is unblocked and can work normally.

 

Preparation before bare cooling: whether each unit equipment is normal after multiple test runs; Instrument control and electric control are put into operation and operate normally. Start the air separation unit according to the normal startup procedure to cool all the equipment and main pipelines in the cold box, and hang frost layers of different degrees. The measuring points meet the technical requirements, and the temperature of each reference point is allowed to be 5-10 ℃ higher in summer. In case of bare cooling, close the valve of liquid hydrogen to liquefaction storage system.

 

Work after bare cooling: tighten the bolts at low temperature with high speed; Sweep the frost in time; Conduct air tightness inspection after heating and inflation.

 

Before the overall cold test, the fractionator shall be fully heated and purged. Air turbine compressor, turbine expander, air precooling system, molecular sieve purification system (or switching system), electrical and instrument control system shall be prepared for good luck.

 

Operation method of cold test:

 

  1. l) During the cold test, the distillation tower, condensing evaporator and other main equipment shall be cooled to the lowest temperature in turn, so that all containers, pipes and their outer surfaces in the cold box are covered with white frost, and shall be maintained for at least 2H.

 

2) During the cold test, organize personnel to enter the cold box (wear cold hat, gloves, cotton clothes, etc.) to strictly check the leakage part and mark it. For the cold valve and low-temperature film regulating valve, the nut can be tightened with special tools, and pay attention to whether the valve is stuck.

 

3) After the cold test (or natural reheating, as long as the manhole is opened), the air tightness test (or dynamic test) shall be carried out. Therefore, all bolts, flange connections, valves and other parts and components need to be tightened again. Pay special attention that the valve cannot be fully closed when tightening. The air tightness test pressure is the same as the working pressure.

 

Generally, the overall cold test shall be conducted twice. According to the leakage and treatment during the test, it is up to the site to decide whether to conduct the cold test again.

 

DEAR air separation requires high quality to promote equipment technology and realize new development of the industry.

DEAR Air Separation Solve YourHow to carry out naked cooling after installation or repair of air separation equipmentYou can also learn about otherLarge air separation FAQ about DEAR Air Separation, and solve the problem for you.
Didn’t find the problem encountered?
Please contact live chat or email for quick help.
Related FAQ
More Related FAQ
Liquid air separation plant cold energy utilises air separation equipment, generally large air separation equipment with 2 combined expanders. The price is around 4 million RMB. The expansion air in the air separation plant is no longer required, so for the internal compression process air separation, the inlet air volume of the circulating booster is reduced by about 40% (from 5.A-2A). The energy consumption of the booster is reduced and the investment is reduced. Liquid air separation equipmen...
2026.06.18
1.In the process of preparation and implementation of hoisting construction, the safety and quality assurance system must ensure the normal operation,to ensure that the hoisting project meets the requirements of safety and quality. Before hoisting, safety and quality inspection must be carried out, and it must comply with the code forLifting construction of chemical engineering construction (HG20201-2000) and other regulations and specifications. 2.The crane performance shall meet the requirements of hoisting process, and the alarm and hydraulic system must be reliable. 3.Strictly implement the provisions of the technical documents attached to the crane. 4.The hoisting schedule of auxiliary crane should match that of main crane. 5.The hook deflection angle shall not be greater than 3°. 6.It is forbidden to drag the unitdirectly on the ground with crane. 7.Before unithoisting, trial hoisting shall be carried out. The clear hoisting distance and the foundation change at
2026.06.17
Need more information?
Contact us for more details about our air separation equipment, solutions and services.
Products
  • Large air separation
  • Small air separation
  • High purity nitrogen air separation
  • Liquefaction air separation
  • Complete air separation
  • Biogas purification
  • Air separation parts
Need more information?
Tel:+86-19837850537
© Kaifeng DEAR Air Separation Industry Co., Ltd.. All rights reserved.
Online
Inquiry
Email
Top