One-week project progress (2012.10.22 -- 2012.10.28)
Oct 22, 2012
Author:
DEAR AST
One-week project progress --- Minyuan 15000 project
● Minyuan KDON (Ar)-15000/15000-500 type complete set of air separation engineering project supporting pipeline is in production, planning to complete production within this week.
One-week project progress --- Shanjun 8000 Project
● KDON (Ar)-8000/2000-240 complete set of air separation engineering project of Jiangsu Shanjun Clean Energy Technology Co., Ltd. Drawings audit and material order of cooling equipment will be completed this week.
One-week project progress --- Shangu 36000 project
● The company signed 36000 m with Xi'an Shangu Power Co., Ltd.3/H air separation plant supply contract, the Design and Research Institute will carry out the relevant equipment drawing design work, it is expected that the drawings of some equipments such as air cooling tower, water cooling tower, lower tower and silencer can be completed in this week.