One-week project progress --- Minyuan 15000 project
● The auxiliary air cooling tower of Minyuan 15000 project has been manufactured by the container branch factory, and now it is entering the final review stage before the pressure test of the equipment; the molecular sieve adsorber is expected to be completed around September 10.
One-week project progress --- Guangxi Chuangui gas 7500 project
● Guangxi Chuangui KDON (Ar)-7500/15000/230 complete air separation project supporting oxygen compressor equipment will be tested in 5th day of this month, and is expected to be delivered in September 7.
One-week project progress --- Shanjun 8000 Project
● The Design and Research Institute of the company is working intensively on the drawing design of cooling equipment related to the contract of Jiangsu Shanjun KDON (Ar)-8000/2000-240 complete air separation project.