One-week project progress --- 1500 project of exporting to Burma
● Burma iron and steel company KDON (Ar)-1500 40Y/1500/40Y complete set of air separation engineering project supporting oxygen compressor equipment will carry out pressure test piping work recently.
● Burma iron and steel company KDON (Ar)-1500 40Y/1500/40Y complete set of air separation engineering project supporting peripheral equipment is being produced by container branch factory, and is expected to be completed around 10th day of this month.
● Burma project supporting distillation column system, purification system and other storage equipment have been finished production, and the work of re-checking is in progress. After the client's inspection and confirmation on 8th day of this month, it is about to enter the stage of packing and delivery.
One-week project progress --- Minyuan 15000 project
● Jinan Iron and Steel Group Minyuan Iron and Steel Co., Ltd. KDON (Ar)-15000/15000-500 complete air separation engineering project supporting tower equipment is manufactured by plate welding branch factory.
● Container branch factory will complete the manufacturing work of supporting water cooling tower equipment of Minyuan 15000 project, which is expected to be completed this month; meanwhile, the supporting air cooling tower equipment of this project is expected to be completed in early September.